Bid tab 0083-07-044

Let Oct 3, 2018 · Atlanta · Camp Sign up free

‹ Oct 2018 results

UPGRADE MBGF

Let date
Wednesday, October 3, 2018
CCSJ
0083-07-044
District
Atlanta
County
Camp
Highway
SH 11
Limits
WOOD C/L to 0.1 MI. W. OF FM 1520
Classification
Construction
Project number
STP 2019(129)HES
Working days
145

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$844,813
1 ODUM SERVICES, LLC Low bidder $934,655 +10.6%
2 CDM HOLDINGS, LLC $963,929 +14.1% +3.1%
3 B & E CONSTRUCTION INC $996,680 +18.0% +6.6%
4 EAST TEXAS BRIDGE, INC. $1,033,358 +22.3% +10.6%
5 HIGHWAY 19 CONSTRUCTION LLC $1,082,125 +28.1% +15.8%
6 FNH CONSTRUCTION, LLC $1,131,745 +34.0% +21.1%
7 TEXCON GENERAL CONTRACTORS $1,179,365 +39.6% +26.2%

Bid tab: unit prices 20 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 ODUM SERVICES, …#2 CDM HOLDINGS, L…#3 B & E CONSTRUCT…#4 EAST TEXAS BRID…#5 HIGHWAY 19 CONS…#6 FNH CONSTRUCTIO…#7 TEXCON GENERAL …
1104-6009 REMOVING CONC (RIPRAP)2,629SY $15.00 $10.00 $23.20 $8.00 $25.00 $25.00 $20.00
2132-6005 EMBANKMENT (FINAL)(ORD COMP)(TY C)200CY $50.00 $30.00 $25.50 $70.00 $30.00 $50.00 $35.00
3164-6071 BROADCAST SEED (TEMP)(WARM OR COOL)700SY $0.2500 $2.00 $4.10 $2.00 $2.00 $1.00 $5.00
4432-6045 RIPRAP (MOW STRIP)(4 IN)481CY $350.00 $600.00 $509.25 $450.00 $445.00 $500.00 $500.00
5451-6004 RETROFIT RAIL (TY T131RC)110LF $220.00 $240.00 $224.10 $260.00 $235.00 $210.00 $200.00
6451-6019 RETROFIT RAIL (TY T631)225LF $100.00 $80.00 $82.50 $105.00 $88.00 $70.00 $200.00
7500-6001 MOBILIZATION1LS $75,620.00 $80,000.00 $66,000.00 $43,736.66 $80,000.00 $180,000.00 $100,000.00
8502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING7MO $2,500.00 $3,000.00 $2,700.00 $6,250.00 $6,000.00 $5,000.00 $8,500.00
9540-6001 MTL W-BEAM GD FEN (TIM POST)9,100LF $20.00 $20.00 $20.40 $23.00 $20.00 $18.00 $22.50
10540-6002 MTL W-BEAM GD FEN (STEEL POST)75LF $80.00 $40.00 $28.55 $95.00 $33.00 $30.00 $65.00
11540-6006 MTL BEAM GD FEN TRANS (THRIE-BEAM)44EA $1,500.00 $1,600.00 $1,660.00 $1,975.00 $1,700.00 $1,500.00 $1,850.00
12540-6016 DOWNSTREAM ANCHOR TERMINAL SECTION14EA $1,100.00 $1,275.00 $1,100.00 $1,350.00 $1,250.00 $1,050.00 $1,850.00
13542-6001 REMOVE METAL BEAM GUARD FENCE10,275LF $2.50 $2.00 $3.10 $3.75 $3.50 $2.60 $3.00
14542-6002 REMOVE TERMINAL ANCHOR SECTION52EA $250.00 $110.00 $170.00 $300.00 $250.00 $150.00 $300.00
15544-6001 GUARDRAIL END TREATMENT (INSTALL)60EA $2,300.00 $2,300.00 $2,450.00 $2,975.00 $2,600.00 $2,375.00 $2,650.00
16544-6003 GUARDRAIL END TREATMENT (REMOVE)26EA $350.00 $250.00 $180.00 $300.00 $200.00 $150.00 $500.00
17658-6048 INSTL OM ASSM (OM-2Z)(FLX)GND204EA $35.00 $55.00 $36.00 $75.00 $40.00 $40.00 $100.00
18672-6007 REFL PAV MRKR TY I-C61EA $5.00 $25.00 $6.00 $30.00 $40.00 $25.00 $15.00
196150-6001 INSTALL SOLAR LED GUARDRAIL MARKER2EA $200.00 $100.00 $800.00 $150.00 $500.00 $7,000.00 $10,000.00
206185-6001 TMA (STATIONARY)2EA $12,000.00 $5,000.00 $22,000.00 $12,000.00 $40,000.00 $30,000.00 $12,500.00