$42.47Avg low bid / LF
$84.42Avg of all bids
$35.82Avg engineer's estimate
5Jobs · 85 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2023 | 1 | 4 | $50.00 | $75.00 |
| 2022 | 1 | 51 | $50.00 | $89.80 |
| 2021 | 1 | 18 | $30.00 | $91.07 |
| 2020 | 1 | 8 | $30.00 | $37.53 |
| 2017 | 1 | 4 | $20.00 | $91.00 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 3, 2023 | 0279-02-048 | FanninParis | 4 LF | $50.00 | HIGHWAY 19 CONSTRUCTION LLC |
| Aug 4, 2022 | 0049-09-089 | BrazosBryan | 51 LF | $50.00 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. |
| May 5, 2021 | 0435-01-080 | LamarParis | 18 LF | $30.00 | HIGHWAY 19 CONSTRUCTION LLC |
| Jul 8, 2020 | 0769-02-033 | LamarParis | 8 LF | $30.00 | D. L. LENNON INCORPORATED - CONTRACTOR |
| Nov 3, 2017 | 0427-02-009 | Red RiverParis | 4 LF | $20.00 | D. L. LENNON INCORPORATED - CONTRACTOR |