$115.00Avg low bid / LF
$100.38Avg of all bids
$91.59Avg engineer's estimate
3Jobs · 5,975 LF
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2021 | 1 | 246 | $300.00 | $207.38 |
| 2019 | 1 | 1,643 | $50.00 | $90.88 |
| 2017 | 1 | 4,086 | $130.00 | $90.00 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Mar 5, 2021 | 0521-06-138 | BexarSan Antonio | 246 LF | $300.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Jul 9, 2019 | 0521-04-204 | BexarSan Antonio | 1,643 LF | $50.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Aug 8, 2017 | 0271-17-161 | HarrisHouston | 4,086 LF | $130.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |