$96.86Avg low bid / CY
$108.47Avg of all bids
$106.59Avg engineer's estimate
13Jobs · 5,404.4 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 1 | 92 | $226.00 | $425.05 |
| 2023 | 1 | 12 | $500.00 | $372.50 |
| 2022 | 1 | 3 | $800.00 | $518.67 |
| 2021 | 1 | 58 | $66.00 | $122.00 |
| 2020 | 1 | 300 | $120.00 | $131.61 |
| 2019 | 5 | 2,373 | $114.88 | $130.77 |
| 2018 | 2 | 159.4 | $146.55 | $152.41 |
| 2017 | 1 | 2,407 | $65.83 | $91.26 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Feb 2, 2024 | 0320-06-008 | BellWaco | 92 CY | $226.00 | JAMES CONSTRUCTION GROUP, LLC |
| Nov 2, 2023 | 6449-59-001 | ChambersBeaumont | 12 CY | $500.00 | STRUCTURAL INTEGRITY GROUP LLC |
| Jan 6, 2022 | 0848-04-049 | MedinaSan Antonio | 3 CY | $800.00 | RELMCO, INC. |
| May 5, 2021 | 2551-01-011 | El PasoEl Paso | 58 CY | $66.00 | J. A. R. CONCRETE, INC. |
| Dec 3, 2020 | 0902-39-035 | Palo PintoFort Worth | 300 CY | $120.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Dec 4, 2019 | 0389-13-062 | HarrisHouston | 14 CY | $400.00 | RAGLE CONSTRUCTION, INC. |
| Aug 7, 2019 | 0025-02-219 | BexarSan Antonio | 1,784 CY | $90.00 | JORDAN FOSTER CONSTRUCTION, LLC |
| Jun 5, 2019 | 0271-14-237 | HarrisHouston | 6 CY | $400.00 | FORDE CONSTRUCTION COMPANY, INC. |
| May 8, 2019 | 3538-01-035 | MontgomeryHouston | 52 CY | $135.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Feb 5, 2019 | 0508-02-120 | ChambersBeaumont | 517 CY | $187.68 | COPASA, INC. |
| Aug 8, 2018 | 3158-01-032 | MontgomeryHouston | 53.4 CY | $100.00 | SMITH & COMPANY |
| May 2, 2018 | 3207-01-011 | JohnsonFort Worth | 106 CY | $170.00 | JAY MILLS CONTRACTING, INCORPORATED |
| Dec 5, 2017 | 0008-13-221 | TarrantFort Worth | 2,407 CY | $65.83 | FLATIRON CONSTRUCTORS, INC. |