$1,170.75Avg low bid / CY
$1,273.45Avg of all bids
$1,013.83Avg engineer's estimate
4Jobs · 699.6 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2019 | 1 | 120.8 | $900.00 | $1,482.24 |
| 2017 | 3 | 578.8 | $1,227.26 | $1,246.53 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Dec 4, 2019 | 0176-03-097 | AngelinaLufkin | 120.8 CY | $900.00 | SACYR CONSTRUCTION USA LLC |
| Dec 6, 2017 | 0440-06-017 | TravisAustin | 223.4 CY | $1,034.17 | OHL USA, INC. |
| Aug 8, 2017 | 0271-17-161 | HarrisHouston | 36.9 CY | $2,200.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Aug 8, 2017 | 3136-01-015 | TravisAustin | 318.5 CY | $1,250.00 | WEBBER, LLC |