$1,008.16Avg low bid / CY
$1,028.11Avg of all bids
$1,011.41Avg engineer's estimate
13Jobs · 14,442.9 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 2 | 3,788.4 | $1,044.27 | $1,106.78 |
| 2022 | 2 | 2,391.1 | $1,393.42 | $1,632.29 |
| 2021 | 2 | 1,820.4 | $1,053.03 | $1,002.89 |
| 2019 | 1 | 75.4 | $900.00 | $1,066.67 |
| 2018 | 2 | 1,572 | $859.29 | $851.26 |
| 2017 | 4 | 4,795.6 | $821.02 | $908.90 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Aug 1, 2024 | 0271-07-326 | HarrisHouston | 399.2 CY | $1,420.13 | WEBBER, LLC |
| May 2, 2024 | 0028-13-135 | JeffersonBeaumont | 3,389.2 CY | $1,000.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Aug 3, 2022 | 0015-10-062 | TravisAustin | 1,745.3 CY | $1,650.00 | PULICE CONSTRUCTION, INC. |
| Mar 3, 2022 | 0739-02-140 | JeffersonBeaumont | 645.8 CY | $700.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Jun 3, 2021 | 2452-02-128 | BexarSan Antonio | 1,404.5 CY | $1,113.15 | ZACHRY CONSTRUCTION CORPORATION |
| Apr 7, 2021 | 2452-02-083 | BexarSan Antonio | 415.9 CY | $850.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Jul 9, 2019 | 0521-04-204 | BexarSan Antonio | 75.4 CY | $900.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Sep 6, 2018 | 0271-16-140 | HarrisHouston | 1,316 CY | $900.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| May 2, 2018 | 0389-05-116 | HarrisHouston | 256 CY | $650.00 | WEBBER, LLC |
| Dec 6, 2017 | 0271-17-163 | HarrisHouston | 830.3 CY | $900.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |
| Oct 4, 2017 | 0111-03-031 | Fort BendHouston | 308.3 CY | $700.00 | PULICE CONSTRUCTION, INC. |
| Aug 9, 2017 | 0015-13-382 | TravisAustin | 1,620.8 CY | $830.00 | J.D. ABRAMS, L.P. |
| Aug 8, 2017 | 0271-17-161 | HarrisHouston | 2,036.2 CY | $800.00 | WILLIAMS BROTHERS CONSTRUCTION CO., INC. |