$17.04Avg low bid / CY
$19.56Avg of all bids
$7.05Avg engineer's estimate
13Jobs · 113,030.8 CY
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 2 | 493 | $36.06 | $75.10 |
| 2021 | 1 | 20 | $50.00 | $87.47 |
| 2020 | 1 | 962 | $25.00 | $31.39 |
| 2019 | 3 | 3,328 | $23.29 | $38.70 |
| 2018 | 1 | 72,154 | $15.60 | $16.70 |
| 2017 | 4 | 2,933.8 | $28.49 | $29.91 |
| 2015 | 1 | 33,140 | $18.00 | $18.76 |
| Let date | CCSJ | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 6, 2024 | 2121-03-171 | El PasoEl Paso | 458 CY | $35.00 | EL PASO A.R.C. ELECTRIC, INC. |
| Feb 1, 2024 | 0014-10-068 | McLennanWaco | 35 CY | $50.00 | E-Z BEL CONSTRUCTION, LLC |
| Mar 17, 2021 | 6376-06-001 | AtascosaSan Antonio | 20 CY | $50.00 | DBI SERVICES, LLC |
| Sep 4, 2020 | 0231-02-062 | CoryellWaco | 962 CY | $25.00 | TTG UTILITIES, LP |
| Dec 3, 2019 | 0011-01-038 | TaylorAbilene | 2,278 CY | $20.00 | BONTKE BROTHERS CONSTRUCTION COMPANY |
| Aug 6, 2019 | 0005-05-114 | HowardAbilene | 930 CY | $27.00 | GRATIOT CONSTRUCTION, LTD. |
| Jun 4, 2019 | 1601-01-034 | ParkerFort Worth | 120 CY | $57.00 | NORTHEASTERN PAVERS, LLC |
| Aug 7, 2018 | 0484-01-023 | JonesAbilene | 72,154 CY | $15.60 | J. H. STRAIN & SONS, INC. |
| Dec 5, 2017 | 0005-05-109 | HowardAbilene | 500 CY | $38.45 | PRICE CONSTRUCTION, LTD. |
| Aug 8, 2017 | 0005-06-119 | HowardAbilene | 1,549 CY | $10.00 | MASSANA CONSTRUCTION INC. |
| Mar 8, 2017 | 0139-08-037 | PecosOdessa | 865 CY | $55.80 | REECE ALBERT, INC. |
| Mar 7, 2017 | 0015-11-063 | TravisAustin | 19.8 CY | $30.00 | OPPORTUNITY EXCAVATION/CONCRETE, LLC |
| May 5, 2015 | 1872-02-017 | HowardAbilene | 33,140 CY | $18.00 | SBBI, INC. |