FY27 - Bryan AO TY B Gr 5 - 11
6511-38-001 · let Nov 17, 2026 · Brazos, Bryan · Material Maintenance Project
$47,904Low bid: COLORADO MATERIALS, LTD.+14.1% vs estimate $42,000
$6,096Left on the table12.7% gap to the second bid
4BiddersSpread 42% low to high
3Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | COLORADO MATERIALS, LTD. | $47,904 | 14.1% | $6,096 | 0 | 0 | |
| 2 | TOUCHSTONE RESOURCES, LLC | $54,000 | +12.7% | 28.6% | $3,008 | 0 | 0 |
| 3 | DIGG COMMERCIAL, LLC | $57,008 | +19.0% | 35.7% | $11,216 | 0 | 0 |
| 4 | MARTIN MARIETTA MATERIALS, INC. | $68,224 | +42.4% | 62.4% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
COLORADO MATERIALS, LTD. vs TOUCHSTONE RESOURCES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8000-7114 AGGR (TY B GR 5) (DEL) (ST2) | 200 TON | $81.14 | $100.00 | $67.10 | $3,772 |
| 8000-7113 AGGR (TY B GR 5) (DEL) (ST1) | 200 TON | $78.02 | $85.00 | $67.38 | $1,396 |
| 8000-7115 AGGR (TY B GR 5) (DEL) (ST3) | 200 TON | $80.36 | $85.00 | $66.22 | $928 |
Positive: the low bidder was cheaper on that item. These 3 items account for $6,096 of the $6,096 gap.