6510-75-001 Bridge Repair Callout
6510-75-001 · let Nov 19, 2026 · Ector, Odessa · Bridge Preventative Maintenance - Sealed
$669,750Low bid: RELMCO, INC.-30.9% vs estimate $969,250
$33,975Left on the table5.1% gap to the second bid
4BiddersSpread 36% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RELMCO, INC. | $669,750 | -30.9% | $33,975 | 2+$44,172 | 0 | |
| 2 | SCR CIVIL CONSTRUCTION, LLC | $703,725 | +5.1% | -27.4% | $17,506 | 2+$58,817 | 0 |
| 3 | PREMIER CONTRACTORS LLC | $721,231 | +7.7% | -25.6% | $191,719 | 1+$31,277 | 3-$48,235 |
| 4 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $912,950 | +36.3% | -5.8% | 6+$318,541 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RELMCO, INC. vs SCR CIVIL CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 429-7005 CONC STR REPAIR(DECK REP (FULL DEPTH)) | 450 SF | $215.00 | $285.00 | $192.68 | $31,500 |
| 788-7002 CONCRETE BEAM REPAIR (CFRP) | 5 EA | $7,250.00 | $13,500.00 | $6,492.05 | $31,250 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 1,500 SF | $185.00 | $166.00 | $150.68 | -$28,500 |
| 788-7003 CONCRETE BEAM REP(STRAND SPLICE & CFRP) | 5 EA | $9,250.00 | $14,500.00 | $10,082.27 | $26,250 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 5 EA | $7,250.00 | $4,000.00 | $5,892.50 | -$16,250 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $2,500.00 | $50.00 | $600.85 | -$14,700 |
| 505-7001 TMA (STATIONARY) | 150 DAY | $150.00 | $225.00 | $217.57 | $11,250 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 40 LF | $350.00 | $595.00 | $380.94 | $9,800 |
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 300 SF | $205.00 | $175.00 | $95.74 | -$9,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 75 DAY | $150.00 | $55.00 | $87.82 | -$7,125 |
| 788-7001 CONCRETE BEAM REPAIR | 10 EA | $5,250.00 | $5,200.00 | $4,623.25 | -$500 |
Positive: the low bidder was cheaper on that item. These 11 items account for $33,975 of the $33,975 gap.
RELMCO, INC.: unbalanced items
Placed 1SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 2PREMIER CONTRACTORS LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 429-7003 CONC STR REPAIR(DECK REP(PART DEPTH)) | 300 SF | $200.00 | $95.74 | 2.09x | $31,277 |
| 505-7001 TMA (STATIONARY) | 150 DAY | $1.00 | $217.57 | 0.00x | -$32,486 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 40 LF | $150.00 | $380.94 | 0.39x | -$9,238 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 75 DAY | $1.00 | $87.82 | 0.01x | -$6,511 |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 788-7001 CONCRETE BEAM REPAIR | 10 EA | $11,956.00 | $4,623.25 | 2.59x | $73,328 |
| 788-7002 CONCRETE BEAM REPAIR (CFRP) | 5 EA | $20,626.00 | $6,492.05 | 3.18x | $70,670 |
| 788-7003 CONCRETE BEAM REP(STRAND SPLICE & CFRP) | 5 EA | $21,258.00 | $10,082.27 | 2.11x | $55,879 |
| 500-7002 MOBILIZATION (CALLOUT) | 6 EA | $9,000.00 | $600.85 | 14.98x | $50,395 |
| 788-7004 CONCRETE BEAM REP (STRAND SPLICE) | 5 EA | $14,522.00 | $5,892.50 | 2.46x | $43,148 |
| 778-7001 CONCRETE RAIL REPAIR (IN-KIND) | 40 LF | $1,009.00 | $380.94 | 2.65x | $25,122 |