FY27 - Brazos Mowing - 11
6510-61-001 · let Nov 17, 2026 · Brazos, Bryan · Routine Maintenance Project
$476,081Low bid: ORTEGA'S LAWN AND LANDSCAPING, LLC-16.6% vs estimate $570,783
$29,017Left on the table6.1% gap to the second bid
9BiddersSpread 100% low to high
13Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ORTEGA'S LAWN AND LANDSCAPING, LLC | $476,081 | -16.6% | $29,017 | 1+$17,597 | 2-$8,382 | |
| 2 | BOEN LANDSCAPING & IRRIGATION, LLC | $505,097 | +6.1% | -11.5% | $14,568 | 2+$9,037 | 1-$6,571 |
| 3 | CENTRAL NORTH CONSTRUCTION, LLC | $519,665 | +9.2% | -9.0% | $92,922 | 0 | 1-$5,860 |
| 4 | R&M INCORPORATED | $612,587 | +28.7% | 7.3% | $12,233 | 0 | 1-$6,808 |
| 5 | SKYLINE CONSTRUCTION PAVING & STRIPING | $624,820 | +31.2% | 9.5% | $59,344 | 0 | 1-$6,097 |
| 6 | ABESCAPE LANDSCAPING, LLC | $684,164 | +43.7% | 19.9% | $29,226 | ||
| 7 | JASCO | $713,390 | +49.8% | 25.0% | $49,358 | ||
| 8 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | $762,748 | +60.2% | 33.6% | $190,984 | ||
| 9 | A M FABRICATION INC. | $953,732 | +100.3% | 67.1% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ORTEGA'S LAWN AND LANDSCAPING, LLC vs BOEN LANDSCAPING & IRRIGATION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 11,478 AC | $32.00 | $36.50 | $38.53 | $51,651 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $5,000.00 | $1,500.00 | $600.85 | -$14,000 |
| 505-7002 TMA (MOBILE OPERATION) | 40 HR | $1.00 | $200.00 | $64.00 | $7,960 |
| 734-7013 LITTER REMOVAL - TRACT (10) | 1,062 AC | $15.99 | $13.00 | $16.58 | -$3,175 |
| 734-7009 LITTER REMOVAL - TRACT (6) | 783 AC | $15.99 | $13.00 | $15.13 | -$2,341 |
| 734-7007 LITTER REMOVAL - TRACT (4) | 714 AC | $15.99 | $13.00 | $15.54 | -$2,135 |
| 734-7014 LITTER REMOVAL - TRACT (11) | 690 AC | $15.99 | $13.00 | $15.81 | -$2,063 |
| 734-7005 LITTER REMOVAL - TRACT (2) | 573 AC | $15.99 | $13.00 | $14.81 | -$1,713 |
| 734-7011 LITTER REMOVAL - TRACT (8) | 501 AC | $15.99 | $13.00 | $14.79 | -$1,498 |
| 734-7010 LITTER REMOVAL - TRACT (7) | 489 AC | $15.99 | $13.00 | $14.05 | -$1,462 |
| 734-7012 LITTER REMOVAL - TRACT (9) | 258 AC | $15.99 | $13.00 | $13.63 | -$771 |
| 734-7006 LITTER REMOVAL - TRACT (3) | 243 AC | $15.99 | $13.00 | $14.49 | -$727 |
| 734-7004 LITTER REMOVAL - TRACT (1) | 237 AC | $15.99 | $13.00 | $40.72 | -$709 |
Positive: the low bidder was cheaper on that item. These 13 items account for $29,017 of the $29,017 gap.
ORTEGA'S LAWN AND LANDSCAPING, LLC: unbalanced items
Placed 1BOEN LANDSCAPING & IRRIGATION, LLC: unbalanced items
Placed 2CENTRAL NORTH CONSTRUCTION, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 734-7004 LITTER REMOVAL - TRACT (1) | 237 AC | $16.00 | $40.72 | 0.39x | -$5,860 |
R&M INCORPORATED: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 734-7004 LITTER REMOVAL - TRACT (1) | 237 AC | $12.00 | $40.72 | 0.29x | -$6,808 |
SKYLINE CONSTRUCTION PAVING & STRIPING: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 734-7004 LITTER REMOVAL - TRACT (1) | 237 AC | $15.00 | $40.72 | 0.37x | -$6,097 |