Mowing of highways ROW - Dimmit
6509-66-001 · let Nov 19, 2026 · Dimmit, Laredo · Routine Maintenance Project - Sealed
$428,848Low bid: BOEN LANDSCAPING & IRRIGATION, LLC-8.9% vs estimate $470,814
$4,186Left on the table1.0% gap to the second bid
4BiddersSpread 27% low to high
4Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BOEN LANDSCAPING & IRRIGATION, LLC | $428,848 | -8.9% | $4,186 | 1+$27,704 | 0 | |
| 2 | ABESCAPE LANDSCAPING, LLC | $433,034 | +1.0% | -8.0% | $25,165 | 0 | 0 |
| 3 | R&M INCORPORATED | $458,199 | +6.8% | -2.7% | $86,841 | 0 | 0 |
| 4 | RICHARDSON BROS. CONTRACTING LLC | $545,040 | +27.1% | 15.8% | 1+$7,704 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
BOEN LANDSCAPING & IRRIGATION, LLC vs ABESCAPE LANDSCAPING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 7,431 AC | $41.00 | $47.00 | $38.53 | $44,586 |
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $3,000.00 | $1.00 | $229.60 | -$29,990 |
| 730-7020 STRIP MOWING | 896 AC | $41.00 | $20.00 | $32.12 | -$18,816 |
| 730-7001 FULL - WIDTH MOWING - TRACT (1) | 1,401 AC | $41.00 | $47.00 | $42.29 | $8,406 |
Positive: the low bidder was cheaper on that item. These 4 items account for $4,186 of the $4,186 gap.
BOEN LANDSCAPING & IRRIGATION, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $3,000.00 | $229.60 | 13.07x | $27,704 |
RICHARDSON BROS. CONTRACTING LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7003 TMA (MOBILE OPERATION) | 10 DAY | $1,000.00 | $229.60 | 4.36x | $7,704 |