MOWING AND LITTER P/U - CORYELL COUNTY
6506-52-001 · let Nov 17, 2026 · Coryell, Waco · Routine Maintenance Project
$254,153Low bid: JASCO-13.9% vs estimate $295,251
$12,683Left on the table5.0% gap to the second bid
8BiddersSpread 130% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JASCO | $254,153 | -13.9% | $12,683 | 0 | 0 | |
| 2 | BOEN LANDSCAPING & IRRIGATION, LLC | $266,837 | +5.0% | -9.6% | $7,785 | 1+$3,597 | 0 |
| 3 | T&L CLEANING SERVICES LLC | $274,622 | +8.1% | -7.0% | $12,145 | 0 | 1-$6,274 |
| 4 | MARLANE CONSTRUCTION, LLC | $286,767 | +12.8% | -2.9% | $48,902 | 0 | 1-$6,274 |
| 5 | ABESCAPE LANDSCAPING, LLC | $335,669 | +32.1% | 13.7% | $45,240 | 0 | 1-$6,274 |
| 6 | CENTRAL NORTH CONSTRUCTION, LLC | $380,910 | +49.9% | 29.0% | $107,538 | ||
| 7 | A M FABRICATION INC. | $488,447 | +92.2% | 65.4% | $95,534 | ||
| 8 | YELLOWSTONE LANDSCAPE - CENTRAL, INC. | $583,982 | +129.8% | 97.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
JASCO vs BOEN LANDSCAPING & IRRIGATION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 730-7022 FULL - WIDTH MOWING | 6,116.22 AC | $34.95 | $36.00 | $38.53 | $6,422 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $1.00 | $1,500.00 | $600.85 | $5,996 |
| 734-7001 LITTER REMOVAL | 2,604.8 AC | $13.00 | $11.00 | $15.14 | -$5,210 |
| 734-7003 LITTER REMOVAL (SPOT) | 500 AC | $13.00 | $22.00 | $13.55 | $4,500 |
| 730-7021 SPOT MOWING | 25 AC | $1.00 | $40.00 | $30.27 | $975 |
Positive: the low bidder was cheaper on that item. These 5 items account for $12,683 of the $12,683 gap.
BOEN LANDSCAPING & IRRIGATION, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $1,500.00 | $600.85 | 2.50x | $3,597 |
T&L CLEANING SERVICES LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 734-7003 LITTER REMOVAL (SPOT) | 500 AC | $1.00 | $13.55 | 0.07x | -$6,274 |
MARLANE CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 734-7003 LITTER REMOVAL (SPOT) | 500 AC | $1.00 | $13.55 | 0.07x | -$6,274 |
ABESCAPE LANDSCAPING, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 734-7003 LITTER REMOVAL (SPOT) | 500 AC | $1.00 | $13.55 | 0.07x | -$6,274 |