| 1 | AR108086 |
1/C #6 XLP-USE | 1,065 | L.F. |
|
$2.57 |
$2.70 |
| 2 | AR108158 |
1/C #8 5 KV UG CABLE IN UD | 530 | L.F. |
|
$5.15 |
$5.39 |
| 3 | AR110202 |
2" PVC DUCT, DIRECT BURY | 345 | L.F. |
|
$9.56 |
$10.01 |
| 4 | AR125441 |
TAXI GUIDANCE SIGN, 1 CHARACTER | 1 | EACH |
|
$3,097.50 |
$3,245.00 |
| 5 | AR125442 |
TAXI GUIDANCE SIGN, 2 CHARACTER | 1 | EACH |
|
$3,097.50 |
$3,245.00 |
| 6 | AR125565 |
SPLICE CAN | 2 | EACH |
|
$997.50 |
$1,045.00 |
| 7 | AR125961 |
RELOCATE STAKE MOUNTED LIGHT | 9 | EACH |
|
$273.00 |
$286.00 |
| 8 | AR150510 |
ENGINEER'S FIELD OFFICE | 1 | L.S. |
|
$10,139.73 |
$18,609.33 |
| 9 | AR150520 |
MOBILIZATION | 1 | L.S. |
|
$41,328.86 |
$72,242.34 |
| 10 | AR150540 |
HAUL ROUTE | 1 | L.S. |
|
$49,304.59 |
$61,168.00 |
| 11 | AR152410 |
UNCLASSIFIED EXCAVATION | 2,026 | C.Y. |
|
$41.90 |
$44.38 |
| 12 | AR152480 |
SHOULDER ADJUSTMENT | 10,200 | S.Y. |
|
$2.64 |
$10.21 |
| 13 | AR154604 |
GRANULAR DRAINAGE SUBBASE - 4" | 4,052 | S.Y. |
|
$11.30 |
$15.83 |
| 14 | AR156510 |
SILT FENCE | 88 | L.F. |
|
$4.56 |
$14.66 |
| 15 | AR156513 |
SEPARATION FABRIC | 8,103 | S.Y. |
|
$1.99 |
$4.90 |
| 16 | AR156530 |
TEMPORARY SEEDING | 2.1 | ACRE |
|
$415.17 |
$66.00 |
| 17 | AR201661 |
CLEAN & SEAL BITUMINOUS CRACKS | 10,000 | L.F. |
|
$2.23 |
$1.93 |
| 18 | AR209604 |
CRUSHED AGG. BASE COURSE - 4" | 4,052 | S.Y. |
|
$9.77 |
$21.19 |
| 19 | AR401614 |
BIT. SURF. CSE.-METHOD II, SUPERPAV | 4,200 | TON |
|
$103.01 |
$126.82 |
| 20 | AR401630 |
BITUMINOUS SURFACE TEST SECTION | 1 | EACH |
|
$7,535.13 |
$9,366.59 |
| 21 | AR401650 |
BITUMINOUS PAVEMENT MILLING | 33,062 | S.Y. |
|
$1.44 |
$3.10 |
| 22 | AR401665 |
BITUMINOUS PAVEMENT SAWING | 7,942 | L.F. |
|
$0.9400 |
$5.95 |
| 23 | AR401910 |
REMOVE & REPLACE BIT. PAVEMENT | 50 | S.Y. |
|
$108.39 |
$72.93 |
| 24 | AR403611 |
BITUMINOUS BASE COURSE-METHOD I | 375 | TON |
|
$109.86 |
$172.73 |
| 25 | AR403673 |
REFLECTIVE CRACK CONTROL TREATMENT | 3,705 | S.Y. |
|
$16.20 |
$16.97 |
| 26 | AR602510 |
BITUMINOUS PRIME COAT | 1,140 | GAL. |
|
$3.90 |
$5.60 |
| 27 | AR603510 |
BITUMINOUS TACK COAT | 7,263 | GAL. |
|
$2.64 |
$3.60 |
| 28 | AR608510 |
EXISTING ASPHALT SURFACE TREATMENT | 1,719 | S.Y. |
|
$6.30 |
$10.00 |
| 29 | AR620520 |
PAVEMENT MARKING-WATERBORNE | 17,986 | S.F. |
|
$0.5900 |
$1.83 |
| 30 | AR620525 |
PAVEMENT MARKING-BLACK BORDER | 6,494 | S.F. |
|
$0.6500 |
$1.86 |
| 31 | AR701521 |
21" RCP, CLASS IV | 352 | L.F. |
|
$83.40 |
$111.62 |
| 32 | AR705526 |
6" PERFORATED UNDERDRAIN W/SOCK | 7,768 | L.F. |
|
$14.03 |
$28.58 |
| 33 | AR705546 |
6" NON PERFORATED UNDERDRAIN | 25 | L.F. |
|
$22.16 |
$43.20 |
| 34 | AR705548 |
8" NON PERFORATED UNDERDRAIN | 302 | L.F. |
|
$29.61 |
$33.75 |
| 35 | AR705620 |
UNDERDRAIN END SECTION | 1 | EACH |
|
$708.75 |
$460.63 |
| 36 | AR705630 |
UNDERDRAIN INSPECTION HOLE | 7 | EACH |
|
$882.91 |
$1,137.60 |
| 37 | AR705635 |
UNDERDRAIN COLLECTION STRUCTURE | 3 | EACH |
|
$2,485.67 |
$6,104.84 |
| 38 | AR705640 |
UNDERDRAIN CLEANOUT | 8 | EACH |
|
$966.13 |
$816.75 |
| 39 | AR705904 |
REMOVE UNDERDRAIN CLEANOUT | 14 | EACH |
|
$331.15 |
$159.05 |
| 40 | AR751540 |
MANHOLE 4' | 1 | EACH |
|
$3,964.12 |
$4,912.58 |
| 41 | AR800589 |
BIT.MILLINGS SUBBASE, 6" | 4,052 | S.Y. |
|
$4.49 |
$14.72 |
| 42 | AR901510 |
SEEDING | 2.1 | ACRE |
|
$3,123.75 |
$3,023.75 |
| 43 | AR908510 |
MULCHING | 2.1 | ACRE |
|
$2,651.25 |
$1,980.00 |