Bid tab ED018

Let Nov 9, 2018 · District 5 · Edgar Start free trial

‹ Nov 2018 results

EDGAR COUNTY

Let date
Friday, November 9, 2018
Contract
ED018
District
District 5
County
Edgar
Highway

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Feutz Contractors, Inc. Low bidder $992,905
2 Beniach Construction Co., Inc. $1,154,780 +16.3%
3 Kieffer Bros. Construction Co., Inc. $1,174,064 +18.2%
4 White Construction, Inc. $1,420,754 +43.1%

Bid tab: unit prices 37 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Feutz Contracto…#2 Beniach Constru…#3 Kieffer Bros. C…#4 White Construct…
1AR108084 1/C #4 XLP-USE1,340L.F. $3.50 $4.00 $3.70 $3.25
2AR108086 1/C #6 XLP-USE760L.F. $3.10 $3.70 $3.36 $3.00
3AR108108 1/C #8 5 KV UG CABLE1,300L.F. $3.30 $3.90 $3.49 $3.00
4AR108158 1/C #8 5 KV UG CABLE IN UD110L.F. $12.50 $15.00 $13.22 $12.00
5AR110504 4-WAY CONCRETE ENCASED DUCT620L.F. $92.00 $107.00 $96.54 $85.00
6AR110710 ELECTRICAL MANHOLE4EACH $5,900.00 $6,971.00 $6,268.71 $5,750.00
7AR125415 MITL-BASE MOUNTED2EACH $1,620.00 $1,893.00 $1,702.94 $1,600.00
8AR150510 ENGINEER'S FIELD OFFICE1L.S. $9,300.00 $11,516.00 $10,303.20 $12,000.00
9AR150520 MOBILIZATION1L.S. $65,000.00 $58,000.00 $50,757.57 $75,000.00
10AR150540 HAUL ROUTE1L.S. $28,000.00 $24,000.00 $7,239.80 $80,000.00
11AR152410 UNCLASSIFIED EXCAVATION545C.Y. $40.00 $27.00 $13.78 $28.00
12AR155540 BY-PRODUCT LIME157TON $120.00 $147.00 $128.26 $125.00
13AR155616 SOIL PROCESSING-16"4,325S.Y. $4.00 $10.00 $9.03 $6.50
14AR156510 SILT FENCE183L.F. $3.70 $5.60 $5.72 $3.00
15AR156511 DITCH CHECK5EACH $540.00 $241.00 $168.22 $8.00
16AR156530 TEMPORARY SEEDING1.1ACRE $1,200.00 $1,919.00 $4,081.00 $11.00
17AR156531 EROSION CONTROL BLANKET1,235S.Y. $1.70 $2.00 $2.05 $1.75
18AR209510 CRUSHED AGGREGATE BASE COURSE1,016TON $35.00 $32.00 $37.31 $80.00
19AR501506 6" PCC PAVEMENT4,325S.Y. $57.00 $70.50 $78.25 $70.00
20AR501530 PCC TEST BATCH1EACH $2,000.00 $1,003.00 $932.80 $3,500.00
21AR620520 PAVEMENT MARKING-WATERBORNE841S.F. $2.00 $2.40 $5.95 $2.00
22AR620525 PAVEMENT MARKING-BLACK BORDER1,030S.F. $2.10 $2.60 $0.8800 $2.25
23AR701900 REMOVE PIPE93L.F. $14.00 $8.70 $11.77 $25.00
24AR705506 6" PERFORATED UNDERDRAIN442L.F. $20.00 $16.90 $15.95 $40.00
25AR705546 6" NON PERFORATED UNDERDRAIN327L.F. $25.00 $21.70 $29.36 $55.00
26AR705620 UNDERDRAIN END SECTION1EACH $350.00 $936.00 $580.35 $1,350.00
27AR705640 UNDERDRAIN CLEANOUT3EACH $875.00 $808.00 $406.83 $2,000.00
28AR751411 INLET-TYPE A1EACH $2,600.00 $1,727.00 $1,887.44 $3,000.00
29AR751900 REMOVE INLET1EACH $330.00 $202.00 $503.50 $1,000.00
30AR752900 REMOVE END SECTION1EACH $265.00 $202.00 $564.45 $1,000.00
31AR800469 REMOVE BITUMINOUS & PCC PAVEMENT707S.Y. $10.00 $14.70 $11.87 $40.00
32AR800494 CONSTRUCT FUELING FACILITY1L.S. $275,000.00 $380,500.00 $397,111.30 $486,000.00
33AR800561 SITE WORK FOR FUELING FACILITY1L.S. $123,000.00 $66,000.00 $76,199.53 $125,000.00
34AR800562 RELOCATE EXISTING FUEL TANK1L.S. $2,700.00 $6,135.00 $2,915.00 $5,000.00
35AR800586 REMOVE EXISTING FUELING FACILITY1L.S. $5,500.00 $28,000.00 $32,913.00 $6,500.00
36AR901510 SEEDING1.1ACRE $2,100.00 $3,100.00 $2,856.70 $2,500.00
37AR908510 MULCHING0.8ACRE $1,600.00 $2,600.00 $2,448.60 $2,300.00