DEKALB TAYLOR MUNICIPAL
- Let date
- Friday, March 6, 2020
- Contract
- DK059
- District
- District 3
- County
- Dekalb
- Highway
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | William Charles Construction Co, LLC Low bidder | $595,000 | ||
| 2 | J. Ranck Electric, Inc. | $756,300 | +27.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 William Charles… | #2 J. Ranck Electr… |
|---|---|---|---|---|---|---|---|
| 1 | AR107408 | L-806 WIND CONE-8' LIGHTED | 1 | EACH | $16,901.65 | $25,000.00 | |
| 2 | AR108158 | 1/C #8 5 KV UG CABLE IN UD | 200 | L.F. | $13.46 | $15.00 | |
| 3 | AR109210 | VAULT MODIFICATIONS | 1 | L.S. | $109,671.74 | $25,000.00 | |
| 4 | AR110014 | 4" DIRECTIONAL BORE | 255 | L.F. | $55.64 | $80.00 | |
| 5 | AR110610 | ELECTRICAL HANDHOLE | 1 | EACH | $9,002.51 | $6,500.00 | |
| 6 | AR125565 | SPLICE CAN | 13 | EACH | $1,975.93 | $1,500.00 | |
| 7 | AR125610 | REILS | 1 | PAIR | $27,899.75 | $25,500.00 | |
| 8 | AR125615 | PAPI (L-880 SYSTEM) | 3 | EACH | $60,430.86 | $79,500.00 | |
| 9 | AR125907 | REMOVE REILS | 1 | PAIR | $4,679.34 | $3,000.00 | |
| 10 | AR125908 | REMOVE PAPI | 2 | EACH | $5,100.26 | $3,000.00 | |
| 11 | AR125910 | REMOVE PLASI | 1 | EACH | $2,591.25 | $1,500.00 | |
| 12 | AR150510 | ENGINEER'S FIELD OFFICE | 1 | L.S. | $11,609.29 | $22,500.00 | |
| 13 | AR150520 | MOBILIZATION | 1 | L.S. | $31,393.08 | $210,850.00 | |
| 14 | AR800140 | 2 1/C #6 XLP-USE, 1/C #10 GND-1" UD | 7,800 | L.F. | $8.90 | $9.00 | |
| 15 | AR800145 | 2 1/C #4XLP-USE,1/C #10 GND1-1/4"UD | 8,300 | L.F. | $9.37 | $9.50 |