DIXON MUNICIPAL
- Let date
- Friday, July 30, 2021
- Contract
- DI032
- District
- District 2
- County
- Lee
- Highway
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | J. F. Edwards Construction Company Low bidder | $623,643 | ||
| 2 | J. Ranck Electric, Inc. | $637,475 | +2.2% | |
| 3 | William Charles Construction Co, LLC | $681,566 | +9.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J. F. Edwards C… | #2 J. Ranck Electr… | #3 William Charles… |
|---|---|---|---|---|---|---|---|---|
| 1 | AR108158 | 1/C #8 5 KV UG CABLE IN UD | 27,450 | L.F. | $6.95 | $5.50 | $5.93 | |
| 2 | AR109210 | VAULT MODIFICATIONS | 1 | L.S. | $27,250.00 | $25,000.00 | $118,656.85 | |
| 3 | AR109321 | 10 KW REGULATOR, STYLE 1 | 2 | EACH | $13,495.00 | $16,500.00 | $12,613.42 | |
| 4 | AR110014 | 4" DIRECTIONAL BORE | 500 | L.F. | $78.00 | $55.00 | $54.77 | |
| 5 | AR115610 | ELECTRICAL HANDHOLE | 1 | EACH | $9,295.00 | $7,500.00 | $5,263.54 | |
| 6 | AR125106 | RELOC. ELEV. RETROREFLECTIVE MARKER | 8 | EACH | $245.00 | $100.00 | $150.46 | |
| 7 | AR125411 | MITL-STAKE MOUNTED-LED | 212 | EACH | $975.00 | $850.00 | $885.89 | |
| 8 | AR125416 | MITL-BASE MOUNTED-LED | 34 | EACH | $1,925.00 | $1,500.00 | $2,341.39 | |
| 9 | AR150510 | ENGINEER'S FIELD OFFICE | 1 | L.S. | $6,600.00 | $16,000.00 | $3,192.52 | |
| 10 | AR150520 | MOBILIZATION | 1 | L.S. | $24,995.00 | $135,650.00 | $63,272.02 | |
| 11 | AR800164 | REMOVE RETROREFLECTIVE MARKER | 197 | EACH | $125.00 | $50.00 | $36.40 |