23-00048-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $769,769 | ||
| 2 | E. T. Simonds Construction Company | $795,598 | +3.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|
| 1 | X6331007 | REM/REP SPBGR RL ELEM | 25 | FOOT | $250.00 | $115.50 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $13,999.00 | $19,263.19 | |
| 3 | Z0011500 | COLD MILL EX SURFACE | 50,687 | SQ YD | $1.15 | $1.02 | |
| 4 | 40600290 | BIT MATLS TACK CT | 22,809 | POUND | $0.0100 | $0.0100 | |
| 5 | 40600370 | LONG JOINT SEALANT | 20,407 | FOOT | $3.15 | $3.18 | |
| 6 | 40604052 | HMA SC IL-9.5 C N70 | 5,968 | TON | $88.00 | $89.21 | |
| 7 | 44201759 | CL D PATCH T4 9 | 47 | SQ YD | $260.00 | $275.54 | |
| 8 | 48100100 | AGGREGATE SHLDS A | 568 | TON | $40.00 | $49.16 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $30,534.77 | $57,556.46 | |
| 10 | 70300100 | SHORT TERM PAVT MKING | 3,705 | FOOT | $2.50 | $1.63 | |
| 11 | 78001110 | PAINT PVT MK LINE 4 | 70,662 | FOOT | $0.1700 | $0.1400 | |
| 12 | 78001180 | PAINT PVT MK LINE 24 | 18 | FOOT | $25.00 | $4.20 | |
| 13 | 78100100 | RAISED REFL PAVT MKR | 256 | EACH | $56.00 | $38.21 |