19-00157-00-RS
- Let date
- Friday, April 24, 2020
- Contract
- 99642 · job page
- District
- District 9
- County
- Williamson
- Highway
- Limits
- Resurfacing Crenshaw Road from Skyline Road to Pease Road.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $834,637 | ||
| 2 | Southern Illinois Asphalt Co., Inc. | $835,627 | +0.1% | |
| 3 | E. T. Simonds Construction Company | $877,630 | +5.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 Southern Illino… | #3 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|---|
| 1 | 40600290 | BIT MATLS TACK CT | 10,200 | POUND | $0.0100 | $0.00 | $0.7900 | |
| 2 | 40600982 | HMA SURF REM BUTT JT | 80 | SQ YD | $15.00 | $41.48 | $57.19 | |
| 3 | 40600990 | TEMPORARY RAMP | 10 | SQ YD | $40.00 | $58.31 | $27.67 | |
| 4 | 40603085 | HMA BC IL-19.0 N70 | 5,600 | TON | $70.00 | $67.79 | $68.53 | |
| 5 | 40604052 | HMA SC IL-9.5 C N70 | 2,180 | TON | $70.00 | $70.93 | $73.59 | |
| 6 | 48100100 | AGGREGATE SHLDS A | 3,740 | TON | $25.00 | $28.13 | $28.63 | |
| 7 | 48203100 | HMA SHOULDERS | 2,030 | TON | $70.00 | $70.79 | $67.26 | |
| 8 | 64200108 | SHOULDER RUM STRIP 8 | 19,200 | FOOT | $0.7000 | $0.7900 | $0.7400 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $24,000.00 | $14,942.20 | $26,687.93 | |
| 10 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $1,730.00 | $5,295.66 | $20,400.85 | |
| 11 | 70300100 | SHORT TERM PAVT MKING | 1,850 | FOOT | $0.5000 | $1.30 | $2.05 | |
| 12 | 70300150 | SHRT TRM PAVT MK REM | 610 | SQ FT | $1.00 | $0.00 | $0.00 | |
| 13 | 70300220 | TEMP PVT MK LINE 4 | 40,330 | FOOT | $0.00 | $0.00 | $0.00 | |
| 14 | 78001110 | PAINT PVT MK LINE 4 | 40,330 | FOOT | $0.1500 | $0.1300 | $0.1400 | |
| 15 | 78100100 | RAISED REFL PAVT MKR | 130 | EACH | $46.00 | $42.39 | $47.51 |