10-00108-00-FP
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Mt. Carmel Stabilization Group, Inc. Low bidder | $600,471 | ||
| 2 | Sierra Bravo Contractors, LLC | $644,343 | +7.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Mt. Carmel Stab… | #2 Sierra Bravo Co… |
|---|---|---|---|---|---|---|---|
| 1 | 30200650 | PROCESS MOD SOIL 12 | 48,450 | SQ YD | $2.50 | $2.57 | |
| 2 | 30201700 | PORTLAND CEMENT | 1,450 | TON | $164.85 | $166.20 | |
| 3 | 40300200 | BIT MATLS PR CT | 70 | TON | $1,057.90 | $1,057.90 | |
| 4 | 40300400 | BIT MATLS C&S CT | 150 | TON | $566.27 | $566.27 | |
| 5 | 40300500 | COVER COAT AGG | 1,325 | TON | $35.98 | $35.98 | |
| 6 | 40300600 | SEAL COAT AGG | 550 | TON | $31.72 | $31.72 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $7,000.00 | $36,472.27 | |
| 8 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $9,200.00 | $18,251.66 |