15-00125-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $184,218 | ||
| 2 | Dees, Inc. | $187,874 | +2.0% | |
| 3 | Samron Midwest Contracting, Inc. | $198,271 | +7.6% | |
| 4 | E. T. Simonds Construction Company | $243,980 | +32.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 Dees, Inc. | #3 Samron Midwest … | #4 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0900064 | MEMBR WTRPR SYS B STR | 138 | SQ YD | $50.58 | $47.00 | $36.00 | $47.29 | |
| 2 | X1200140 | PCBC SPL | 52 | FOOT | $1,402.30 | $1,700.00 | $1,800.00 | $1,686.86 | |
| 3 | X2070302 | POROUS GRAN EMB SPEC | 500 | TON | $27.44 | $22.00 | $30.00 | $32.11 | |
| 4 | X2090210 | POROUS GRAN BACK SPEC | 60 | CU YD | $59.10 | $50.00 | $85.00 | $106.57 | |
| 5 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $12,900.00 | $12,000.00 | $12,675.00 | $12,384.97 | |
| 6 | 20100110 | TREE REMOV 6-15 | 48 | UNIT | $27.75 | $50.00 | $25.00 | $71.09 | |
| 7 | 20200100 | EARTH EXCAVATION | 280 | CU YD | $19.69 | $15.00 | $10.00 | $63.26 | |
| 8 | 28100807 | STONE DUMP RIP CL A4 | 200 | TON | $35.57 | $26.00 | $40.00 | $37.77 | |
| 9 | 40200800 | AGG SURF CSE B | 415 | TON | $38.22 | $23.00 | $35.00 | $33.17 | |
| 10 | 50100100 | REM EXIST STRUCT | 1 | EACH | $5,328.03 | $9,000.00 | $5,500.00 | $12,683.10 | |
| 11 | 51500100 | NAME PLATES | 1 | EACH | $507.56 | $400.00 | $350.00 | $622.11 | |
| 12 | 54001001 | BOX CUL END SEC C1 | 2 | EACH | $15,451.39 | $15,000.00 | $11,000.00 | $17,322.02 | |
| 13 | 542D0229 | P CUL CL D 1 24 | 81 | FOOT | $39.04 | $31.00 | $65.00 | $79.56 | |
| 14 | 542D0235 | P CUL CL D 1 30 | 52 | FOOT | $58.34 | $41.00 | $80.00 | $81.44 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $10,427.43 | $10,000.00 | $12,000.00 | $22,499.49 |