19-04120-00-BR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | C-Hill Civil Contractors, Inc. Low bidder | $498,888 | ||
| 2 | Keeley & Sons, Inc. | $717,985 | +43.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 C-Hill Civil Co… | #2 Keeley & Sons, … |
|---|---|---|---|---|---|---|---|
| 1 | X2070302 | POROUS GRAN EMB SPEC | 126 | TON | $50.00 | $59.85 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.75 | ACRE | $6,500.00 | $8,160.00 | |
| 3 | X2810808 | STONE DMP RIP C A4 SP | 161 | TON | $75.00 | $69.15 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,675.00 | $4,890.00 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 7 | 20100500 | TREE REMOV ACRES | 0.6 | ACRE | $11,200.00 | $16,570.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 105 | CU YD | $55.00 | $44.80 | |
| 9 | 20300100 | CHANNEL EXCAVATION | 205 | CU YD | $40.00 | $59.85 | |
| 10 | 20400800 | FURNISHED EXCAVATION | 700 | CU YD | $45.00 | $53.45 | |
| 11 | 40200800 | AGG SURF COURSE TY B | 473 | TON | $50.00 | $59.85 | |
| 12 | 50100100 | REM EXIST STRUCT | 1 | EACH | $16,700.00 | $39,800.00 | |
| 13 | 50300225 | CONC STRUCT | 32.6 | CU YD | $1,000.00 | $3,980.15 | |
| 14 | 50300280 | CONCRETE ENCASEMENT | 2.8 | CU YD | $1,200.00 | $2,285.30 | |
| 15 | 50400605 | P P CONC DK BM 33 DP | 1,872 | SQ FT | $114.00 | $131.85 | |
| 16 | 50800205 | REINF BARS, EPOXY CTD | 5,120 | POUND | $2.50 | $4.35 | |
| 17 | 50900205 | STEEL RAILING TY S1 | 160 | FOOT | $150.00 | $153.77 | |
| 18 | 51201600 | FUR STL PILE HP12X53 | 545 | FOOT | $44.00 | $97.65 | |
| 19 | 51202305 | DRIVING PILES | 545 | FOOT | $0.0100 | $0.0100 | |
| 20 | 51203600 | TEST PILE ST HP12X53 | 1 | EACH | $40,000.00 | $11,890.00 | |
| 21 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $995.00 | |
| 22 | 63100075 | TRAF BAR TERM T5A | 2 | EACH | $1,365.00 | $1,326.00 | |
| 23 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,570.00 | $3,468.00 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $10,826.55 | $42,250.00 | |
| 25 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $42.00 | $40.80 |