14-14118-00-BR
- Let date
- Friday, November 8, 2019
- Contract
- 97693 · job page
- District
- District 8
- County
- Washington
- Highway
- Limits
- Replace bridge carrying Jimtown Road over Elkhorn Creek.
- Classification
- ·
- Project number
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $363,206 | ||
| 2 | Lake Contracting, Inc. | $367,435 | +1.2% | |
| 3 | Depew and Owen Builders, Inc. | $385,888 | +6.2% | |
| 4 | E. T. Simonds Construction Company | $472,585 | +30.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 Lake Contractin… | #3 Depew and Owen … | #4 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.9 | ACRE | $4,700.00 | $7,500.00 | $6,500.00 | $4,675.00 | |
| 2 | X2810808 | STONE DMP RIP C A4 SP | 306 | TON | $34.00 | $41.00 | $33.00 | $60.49 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $2,000.00 | $4,200.00 | $2,500.00 | $5,618.97 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $6,000.00 | $8,500.00 | $5,000.00 | $13,090.00 | |
| 5 | 20100500 | TREE REMOV ACRES | 0.5 | ACRE | $14,500.00 | $37,000.00 | $12,000.00 | $36,170.76 | |
| 6 | 20200100 | EARTH EXCAVATION | 955 | CU YD | $13.50 | $8.50 | $14.00 | $21.90 | |
| 7 | 20300100 | CHANNEL EXCAVATION | 210 | CU YD | $15.00 | $8.50 | $25.00 | $25.53 | |
| 8 | 20400800 | FURNISHED EXCAVATION | 2,185 | CU YD | $13.00 | $9.50 | $17.00 | $23.80 | |
| 9 | 28000250 | TEMP EROS CONTR SEED | 90 | POUND | $1.00 | $1.00 | $6.00 | $3.28 | |
| 10 | 28000305 | TEMP DITCH CHECKS | 110 | FOOT | $9.00 | $9.00 | $12.00 | $18.25 | |
| 11 | 40200800 | AGG SURF CSE B | 686 | TON | $35.00 | $31.00 | $30.00 | $33.60 | |
| 12 | 40300200 | BIT MATLS PR CT | 8.9 | TON | $850.00 | $520.00 | $0.0100 | $876.98 | |
| 13 | 40300400 | BIT MATLS C&S CT | 4.7 | TON | $600.00 | $865.00 | $1,950.00 | $605.00 | |
| 14 | 40300500 | COVER COAT AGG | 38 | TON | $36.00 | $24.00 | $75.00 | $37.40 | |
| 15 | 40300600 | SEAL COAT AGG | 19 | TON | $36.00 | $24.00 | $75.00 | $37.40 | |
| 16 | 50100100 | REM EXIST STRUCT | 1 | EACH | $3,500.00 | $6,000.00 | $10,000.00 | $10,637.64 | |
| 17 | 50105220 | PIPE CULVERT REMOV | 20 | FOOT | $10.00 | $10.00 | $10.00 | $12.81 | |
| 18 | 50300225 | CONC STRUCT | 24.8 | CU YD | $565.00 | $575.00 | $700.00 | $861.32 | |
| 19 | 50300280 | CONCRETE ENCASEMENT | 2.8 | CU YD | $460.00 | $575.00 | $700.00 | $856.09 | |
| 20 | 50400605 | P P CONC DK BM 33 DP | 1,888 | SQ FT | $80.00 | $76.00 | $85.00 | $85.57 | |
| 21 | 50800105 | REINFORCEMENT BARS | 4,140 | POUND | $1.50 | $1.10 | $2.00 | $1.98 | |
| 22 | 50900205 | STEEL RAILING TY S1 | 160 | FOOT | $105.00 | $108.00 | $95.00 | $101.20 | |
| 23 | 51201600 | FUR STL PILE HP12X53 | 308 | FOOT | $84.00 | $76.50 | $28.00 | $91.28 | |
| 24 | 51202305 | DRIVING PILES | 308 | FOOT | $1.00 | $2.00 | $1.00 | $1.00 | |
| 25 | 51203600 | TEST PILE ST HP12X53 | 1 | EACH | $4,200.00 | $5,000.00 | $10,000.00 | $5,377.14 | |
| 26 | 51500100 | NAME PLATES | 1 | EACH | $350.00 | $350.00 | $400.00 | $477.15 | |
| 27 | 542C0235 | P CUL CL C 1 30 | 44 | FOOT | $56.00 | $60.00 | $85.00 | $83.52 | |
| 28 | 59300100 | CONTR LOW-STRENG MATL | 52.8 | CU YD | $8.00 | $90.00 | $100.00 | $133.09 | |
| 29 | 63100075 | TRAF BAR TERM T5A | 2 | EACH | $1,600.00 | $1,700.00 | $2,450.00 | $1,650.00 | |
| 30 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $4,000.00 | $3,800.00 | $3,500.00 | $3,300.00 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $12,500.00 | $17,500.00 | $9,587.91 | $20,150.33 | |
| 32 | 72000100 | SIGN PANEL T1 | 18 | SQ FT | $25.00 | $34.00 | $30.00 | $27.50 | |
| 33 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $32.00 | $42.00 | $40.00 | $33.00 | |
| 34 | 72900200 | METAL POST TY B | 31 | FOOT | $13.00 | $9.00 | $25.00 | $13.20 |