19-05125-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | C-Hill Civil Contractors, Inc. Low bidder | $310,889 | ||
| 2 | Lake Contracting, Inc. | $345,515 | +11.1% | |
| 3 | Keller Construction, Inc. | $507,392 | +63.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 C-Hill Civil Co… | #2 Lake Contractin… | #3 Keller Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $6,500.00 | $13,500.00 | $15,400.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $1,924.00 | $2,500.00 | $3,600.00 | |
| 3 | 20100500 | TREE REMOV ACRES | 0.24 | ACRE | $25,000.00 | $67,000.00 | $33,500.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 223 | CU YD | $15.00 | $30.00 | $100.00 | |
| 5 | 20300100 | CHANNEL EXCAVATION | 282 | CU YD | $15.00 | $30.00 | $42.00 | |
| 6 | 20400800 | FURNISHED EXCAVATION | 209 | CU YD | $40.00 | $70.00 | $72.00 | |
| 7 | 20700110 | POROUS GRAN EMBANK | 92 | TON | $35.00 | $30.00 | $103.00 | |
| 8 | 28100807 | STONE DUMP RIP CL A4 | 185 | TON | $50.00 | $50.00 | $88.00 | |
| 9 | 40200800 | AGG SURF CSE B | 377 | TON | $38.00 | $35.00 | $58.50 | |
| 10 | 50100100 | REM EXIST STRUCT | 1 | EACH | $10,500.00 | $15,000.00 | $30,000.00 | |
| 11 | 50105220 | PIPE CULVERT REMOV | 20 | FOOT | $25.00 | $10.00 | $19.00 | |
| 12 | 50300225 | CONC STRUCT | 29.2 | CU YD | $750.00 | $700.00 | $1,160.00 | |
| 13 | 50300280 | CONCRETE ENCASEMENT | 2.8 | CU YD | $750.00 | $700.00 | $1,725.00 | |
| 14 | 50400505 | P P CONC DK BM 27 DP | 1,296 | SQ FT | $111.00 | $106.00 | $135.00 | |
| 15 | 50800105 | REINFORCEMENT BARS | 4,490 | POUND | $2.00 | $2.00 | $2.40 | |
| 16 | 50900205 | STEEL RAILING TY S1 | 112 | FOOT | $161.00 | $188.00 | $168.00 | |
| 17 | 51201600 | FUR STL PILE HP12X53 | 388 | FOOT | $46.00 | $80.00 | $110.00 | |
| 18 | 51202305 | DRIVING PILES | 388 | FOOT | $0.0100 | $1.00 | $0.0100 | |
| 19 | 51203600 | TEST PILE ST HP12X53 | 1 | EACH | $15,000.00 | $12,000.00 | $14,500.00 | |
| 20 | 51204650 | PILE SHOES | 8 | EACH | $126.50 | $200.00 | $110.00 | |
| 21 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $400.00 | $888.00 | |
| 22 | 542D0223 | P CUL CL D 1 18 | 66 | FOOT | $85.00 | $50.00 | $84.00 | |
| 23 | 67100100 | MOBILIZATION | 1 | L SUM | $12,250.00 | $14,000.00 | $55,800.00 | |
| 24 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $48.00 | $40.00 | $50.00 |