20-00301-00-PV
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $3,559,453 | ||
| 2 | Dunn Company | $3,609,120 | +1.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 Dunn Company |
|---|---|---|---|---|---|---|---|
| 1 | LR400005 | CIR-FDR EMULS ASPHALT | 113,458 | GALLON | $3.10 | $3.05 | |
| 2 | LR400015 | ADD ROCK | 37,896 | SQ YD | $2.94 | $2.90 | |
| 3 | LR400740 | CIP RECYCLING 4.0 | 28,900 | SQ YD | $3.52 | $3.45 | |
| 4 | LR400750 | CIP RECYCLING 5.0 | 37,896 | SQ YD | $3.83 | $3.65 | |
| 5 | LR403300 | SURFACE PROFILE MILL | 22,168 | SQ YD | $3.68 | $3.10 | |
| 6 | X0327902 | MAILBOX REM & REPL | 6 | EACH | $284.68 | $350.00 | |
| 7 | X2501000 | SEEDING CL 2 SPL | 0.75 | ACRE | $7,980.00 | $13,350.00 | |
| 8 | X6660445 | ROW/PROPERTY CORNERS | 8 | EACH | $345.93 | $375.00 | |
| 9 | Z0004542 | HMA REMOVAL SPL | 324 | SQ YD | $38.38 | $92.40 | |
| 10 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $8,003.53 | $6,500.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 83 | CU YD | $142.47 | $112.00 | |
| 12 | 20400800 | FURNISHED EXCAVATION | 400 | CU YD | $75.61 | $42.00 | |
| 13 | 28000305 | TEMP DITCH CHECKS | 144 | FOOT | $13.23 | $56.00 | |
| 14 | 35102000 | AGG BASE CSE B 8 | 6,959 | SQ YD | $39.05 | $43.20 | |
| 15 | 40200800 | AGG SURF CSE B | 16 | TON | $29.40 | $35.00 | |
| 16 | 40600290 | BIT MATLS TACK CT | 48,120 | POUND | $0.9400 | $0.7000 | |
| 17 | 40600370 | LONG JOINT SEALANT | 28,679 | FOOT | $2.83 | $3.40 | |
| 18 | 40600982 | HMA SURF REM BUTT JT | 1,350 | SQ YD | $19.65 | $22.10 | |
| 19 | 40600990 | TEMPORARY RAMP | 113.2 | SQ YD | $12.62 | $32.50 | |
| 20 | 40602970 | HMA BC IL-9.5FG N70 | 5,888 | TON | $141.70 | $146.20 | |
| 21 | 40604052 | HMA SC IL-9.5 C N70 | 7,935 | TON | $138.81 | $139.35 | |
| 22 | 40800025 | BIT MATLS PR CT | 586 | POUND | $1.25 | $4.10 | |
| 23 | 40800050 | INCIDENTAL HMA SURF | 362 | TON | $289.65 | $220.90 | |
| 24 | 48102100 | AGG WEDGE SHLD TYPE B | 3,848 | TON | $29.40 | $32.20 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $50,740.31 | $37,980.00 | |
| 26 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $4,851.10 | $26,250.00 | |
| 27 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $32,691.46 | $38,470.00 | |
| 28 | 70300100 | SHORT TERM PAVT MKING | 6,916 | FOOT | $1.39 | $0.8500 | |
| 29 | 70300150 | SHRT TRM PAVT MK REM | 964 | SQ FT | $4.31 | $0.9500 | |
| 30 | 78000100 | THPL PVT MK LTR & SYM | 61.2 | SQ FT | $28.88 | $37.15 | |
| 31 | 78000650 | THPL PVT MK LINE 24 | 72 | FOOT | $30.98 | $39.85 | |
| 32 | 78001110 | PAINT PVT MK LINE 4 | 14,687 | FOOT | $0.4000 | $0.5000 |