17-00098-00-BR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Howell Paving, Inc. Low bidder | $914,445 | ||
| 2 | Depew and Owen Builders, Inc. | $969,888 | +6.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Howell Paving, … | #2 Depew and Owen … |
|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $11,700.00 | $8,800.00 | |
| 2 | 20100500 | TREE REMOV ACRES | 0.3 | ACRE | $14,246.27 | $15,000.00 | |
| 3 | 20200100 | EARTH EXCAVATION | 307 | CU YD | $12.34 | $20.00 | |
| 4 | 20300100 | CHANNEL EXCAVATION | 561 | CU YD | $19.30 | $20.00 | |
| 5 | 28000305 | TEMP DITCH CHECKS | 16 | FOOT | $12.42 | $14.00 | |
| 6 | 28100807 | STONE DUMP RIP CL A4 | 791 | TON | $71.62 | $65.00 | |
| 7 | 35101400 | AGG BASE CSE B | 495 | TON | $33.05 | $36.00 | |
| 8 | 40600275 | BIT MATLS PR CT | 1,516 | POUND | $2.98 | $3.00 | |
| 9 | 40600290 | BIT MATLS TACK CT | 152 | POUND | $4.46 | $4.50 | |
| 10 | 40603080 | HMA BC IL-19.0 N50 | 94 | TON | $209.43 | $210.00 | |
| 11 | 40604050 | HMA SC IL-9.5 C N50 | 57 | TON | $297.84 | $298.00 | |
| 12 | 48101500 | AGGREGATE SHLDS B 6 | 245 | SQ YD | $16.32 | $25.00 | |
| 13 | 50100100 | REM EXIST STRUCT | 1 | EACH | $24,791.08 | $25,000.00 | |
| 14 | 50200100 | STRUCTURE EXCAVATION | 127 | CU YD | $19.84 | $20.00 | |
| 15 | 50200300 | COFFERDAM EXCAVATION | 250 | CU YD | $30.49 | $20.00 | |
| 16 | 50201101 | COFFERDAM TYP 1 LOC 1 | 1 | EACH | $8,010.24 | $22,500.00 | |
| 17 | 50201102 | COFFERDAM TYP 1 LOC 2 | 1 | EACH | $8,010.24 | $22,500.00 | |
| 18 | 50300225 | CONC STRUCT | 222 | CU YD | $690.08 | $700.00 | |
| 19 | 50400305 | P P CONC DK BM 17 DP | 3,665 | SQ FT | $95.36 | $94.00 | |
| 20 | 50800205 | REINF BARS, EPOXY CTD | 18,440 | POUND | $1.98 | $2.00 | |
| 21 | 50901050 | STEEL RAILING TY SM | 250 | FOOT | $207.40 | $208.00 | |
| 22 | 51200957 | FUR M S PILE 12X0.250 | 966 | FOOT | $69.42 | $40.00 | |
| 23 | 51202305 | DRIVING PILES | 966 | FOOT | $0.0100 | $1.00 | |
| 24 | 51203200 | TEST PILE MET SHELLS | 4 | EACH | $3,833.95 | $14,250.00 | |
| 25 | 51204650 | PILE SHOES | 30 | EACH | $521.25 | $600.00 | |
| 26 | 51500100 | NAME PLATES | 1 | EACH | $480.68 | $460.00 | |
| 27 | 59300100 | CONTR LOW-STRENG MATL | 58 | CU YD | $131.27 | $95.00 | |
| 28 | 63100087 | TRAF BAR TERM T6A | 2 | EACH | $4,160.00 | $4,160.00 | |
| 29 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,720.00 | $3,720.00 | |
| 30 | 67100100 | MOBILIZATION | 1 | L SUM | $8,903.97 | $25,000.00 | |
| 31 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $42.50 | $45.00 |