19-15146-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $583,078 | ||
| 2 | Sierra Bravo Contractors, LLC | $588,549 | +0.9% | |
| 3 | Samron Midwest Contracting, Inc. | $711,208 | +22.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Sierra Bravo Co… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.6 | ACRE | $11,285.67 | $7,632.00 | $5,300.00 | |
| 2 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $4,070.67 | $8,105.01 | $4,500.00 | |
| 3 | 20200100 | EARTH EXCAVATION | 248 | CU YD | $15.40 | $27.26 | $16.50 | |
| 4 | 20300100 | CHANNEL EXCAVATION | 675 | CU YD | $13.20 | $27.78 | $14.00 | |
| 5 | 20700110 | POROUS GRAN EMBANK | 94 | TON | $36.47 | $38.81 | $37.00 | |
| 6 | 28100807 | STONE DUMP RIP CL A4 | 330 | TON | $41.97 | $49.61 | $43.00 | |
| 7 | 40200800 | AGG SURF CSE B | 180 | TON | $36.47 | $34.30 | $37.00 | |
| 8 | 50100100 | REM EXIST STRUCT | 1 | EACH | $3,850.00 | $61,916.22 | $24,000.00 | |
| 9 | 50300225 | CONC STRUCT | 35.7 | CU YD | $1,344.19 | $1,321.92 | $1,900.00 | |
| 10 | 50300255 | CONC SUP-STR | 121.2 | CU YD | $1,283.01 | $1,393.61 | $2,000.00 | |
| 11 | 50300280 | CONCRETE ENCASEMENT | 27.3 | CU YD | $1,091.23 | $1,393.54 | $1,650.00 | |
| 12 | 50300300 | PROTECTIVE COAT | 306 | SQ YD | $5.41 | $2.47 | $3.00 | |
| 13 | 50800205 | REINF BARS, EPOXY CTD | 57,390 | POUND | $1.57 | $1.32 | $1.50 | |
| 14 | 50900205 | STEEL RAILING TY S1 | 190 | FOOT | $178.81 | $184.97 | $190.00 | |
| 15 | 51200957 | FUR M S PILE 12X0.250 | 710 | FOOT | $96.81 | $70.54 | $115.00 | |
| 16 | 51202305 | DRIVING PILES | 710 | FOOT | $1.00 | $1.00 | $0.00 | |
| 17 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $6,304.55 | $5,970.53 | $20,000.00 | |
| 18 | 51500100 | NAME PLATES | 1 | EACH | $330.00 | $795.00 | $450.00 | |
| 19 | 67100100 | MOBILIZATION | 1 | L SUM | $90,242.75 | $32,751.48 | $41,000.00 | |
| 20 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $44.00 | $41.34 | $45.00 |