18-00122-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $538,450 | ||
| 2 | Depew and Owen Builders, Inc. | $571,488 | +6.1% | |
| 3 | Kieffer Bros. Construction Co., Inc. | $630,536 | +17.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 Depew and Owen … | #3 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.3 | ACRE | $6,800.00 | $4,500.00 | $13,029.50 | |
| 2 | 20200100 | EARTH EXCAVATION | 60 | CU YD | $12.50 | $15.00 | $20.60 | |
| 3 | 20300100 | CHANNEL EXCAVATION | 250 | CU YD | $12.50 | $18.00 | $20.60 | |
| 4 | 20400800 | FURNISHED EXCAVATION | 175 | CU YD | $19.00 | $25.00 | $38.00 | |
| 5 | 28100809 | STONE DUMP RIP CL A5 | 710 | TON | $50.00 | $41.00 | $49.00 | |
| 6 | 35101400 | AGG BASE CSE B | 524 | TON | $27.50 | $30.00 | $39.50 | |
| 7 | 40600275 | BIT MATLS PR CT | 2,176 | POUND | $0.6000 | $0.6000 | $1.00 | |
| 8 | 40600290 | BIT MATLS TACK CT | 804 | POUND | $0.3500 | $0.3500 | $1.00 | |
| 9 | 40600982 | HMA SURF REM BUTT JT | 146 | SQ YD | $19.00 | $25.25 | $28.00 | |
| 10 | 40603085 | HMA BC IL-19.0 N70 | 450 | TON | $110.00 | $102.00 | $114.62 | |
| 11 | 40604052 | HMA SC IL-9.5 C N70 | 300 | TON | $125.00 | $113.00 | $127.52 | |
| 12 | 48101500 | AGGREGATE SHLDS B 6 | 516 | SQ YD | $20.00 | $15.00 | $19.00 | |
| 13 | 50100100 | REM EXIST STRUCT | 1 | EACH | $10,000.00 | $10,000.00 | $16,603.00 | |
| 14 | 50300225 | CONC STRUCT | 31.8 | CU YD | $550.00 | $800.00 | $1,408.26 | |
| 15 | 50400605 | P P CONC DK BM 33 DP | 2,580 | SQ FT | $85.00 | $98.00 | $93.86 | |
| 16 | 50800205 | REINF BARS, EPOXY CTD | 3,920 | POUND | $1.50 | $2.00 | $4.00 | |
| 17 | 50901050 | STEEL RAILING TY SM | 171 | FOOT | $125.00 | $158.00 | $178.00 | |
| 18 | 51201400 | FUR STL PILE HP10X42 | 825 | FOOT | $30.00 | $25.00 | $24.00 | |
| 19 | 51202305 | DRIVING PILES | 825 | FOOT | $0.00 | $1.00 | $4.00 | |
| 20 | 51203400 | TEST PILE ST HP10X42 | 1 | EACH | $10,000.00 | $15,500.00 | $11,494.00 | |
| 21 | 51500100 | NAME PLATES | 1 | EACH | $350.00 | $341.50 | $821.00 | |
| 22 | 542D0229 | P CUL CL D 1 24 | 120 | FOOT | $35.00 | $35.00 | $60.00 | |
| 23 | 63000001 | SPBGR TY A 6FT POSTS | 50 | FOOT | $35.00 | $24.00 | $27.14 | |
| 24 | 63100087 | TRAF BAR TERM T6A | 4 | EACH | $4,200.00 | $3,480.00 | $3,942.00 | |
| 25 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,200.00 | $2,985.00 | $3,382.00 | |
| 26 | 63200310 | GUARDRAIL REMOV | 156 | FOOT | $4.00 | $5.00 | $13.00 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $32,000.00 | $30,000.00 | $26,156.00 | |
| 28 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $40.00 | $45.00 | |
| 29 | 78200005 | GRDRAIL REF TYPE A | 10 | EACH | $10.00 | $9.00 | $10.20 |