17-15145-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $229,550 | ||
| 2 | E. T. Simonds Construction Company | $262,682 | +14.4% | |
| 3 | Allendale Gravel Co., Inc. | $344,354 | +50.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… | #3 Allendale Grave… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0900064 | MEMBR WTRPR SYS B STR | 89 | SQ YD | $50.00 | $57.43 | $105.00 | |
| 2 | X2070302 | POROUS GRAN EMB SPEC | 430 | TON | $25.00 | $38.89 | $25.00 | |
| 3 | X2090210 | POROUS GRAN BACK SPEC | 16 | CU YD | $82.00 | $123.24 | $230.00 | |
| 4 | X2501000 | SEEDING CL 2 SPL | 0.75 | ACRE | $5,250.00 | $5,775.00 | $6,000.00 | |
| 5 | 20100110 | TREE REMOV 6-15 | 75 | UNIT | $25.00 | $49.70 | $27.00 | |
| 6 | 20100210 | TREE REMOV OVER 15 | 100 | UNIT | $25.00 | $52.92 | $22.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 269 | CU YD | $30.00 | $45.08 | $30.00 | |
| 8 | 28100807 | STONE DUMP RIP CL A4 | 140 | TON | $45.00 | $52.24 | $44.00 | |
| 9 | 40200800 | AGG SURF CSE B | 330 | TON | $30.00 | $38.50 | $46.00 | |
| 10 | 50100100 | REM EXIST STRUCT | 1 | EACH | $6,800.00 | $6,709.36 | $28,000.00 | |
| 11 | 50800205 | REINF BARS, EPOXY CTD | 27,370 | POUND | $1.15 | $1.24 | $1.70 | |
| 12 | 50900205 | STEEL RAILING TY S1 | 40 | FOOT | $210.00 | $286.55 | $300.00 | |
| 13 | 51500100 | NAME PLATES | 1 | EACH | $375.00 | $470.30 | $400.00 | |
| 14 | 54003000 | CONC BOX CUL | 106.3 | CU YD | $915.00 | $974.36 | $1,650.00 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $36,000.00 | $37,049.78 | $20,000.00 | |
| 16 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $35.00 | $44.00 | $30.00 |