19-00062-03-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Ne-Co Asphalt Co., Inc. Low bidder | $254,906 | ||
| 2 | Illinois Valley Paving, a div of UCM, Inc. | $319,469 | +25.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Ne-Co Asphalt C… | #2 Illinois Valley… |
|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $14,900.00 | $16,332.27 | |
| 2 | 40600290 | BIT MATLS TACK CT | 9,600 | POUND | $0.4000 | $1.13 | |
| 3 | 40600635 | LEV BIND MM N70 | 1,195 | TON | $82.00 | $97.19 | |
| 4 | 40600982 | HMA SURF REM BUTT JT | 456 | SQ YD | $7.00 | $20.08 | |
| 5 | 40600990 | TEMPORARY RAMP | 108 | SQ YD | $5.00 | $8.96 | |
| 6 | 40603315 | HMA SC "C" N70 | 1,195 | TON | $82.00 | $97.19 | |
| 7 | 40800050 | INCIDENTAL HMA SURF | 119 | TON | $150.00 | $215.94 | |
| 8 | 48102100 | AGG WEDGE SHLD TYPE B | 626 | TON | $18.00 | $23.40 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $3,500.00 | $4,678.59 | |
| 10 | 70300100 | SHORT TERM PAVT MKING | 1,068 | FOOT | $0.5000 | $0.7600 | |
| 11 | 70300150 | SHRT TRM PAVT MK REM | 178 | SQ FT | $3.00 | $7.56 | |
| 12 | 78001110 | PAINT PVT MK LINE 4 | 1,330 | FOOT | $2.00 | $1.95 | |
| 13 | 78001150 | PAINT PVT MK LINE 12 | 18 | FOOT | $6.00 | $5.87 |