13-05123-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lake Contracting, Inc. Low bidder | $244,759 | ||
| 2 | Allendale Gravel Co., Inc. | $316,100 | +29.1% | |
| 3 | Kieffer Bros. Construction Co., Inc. | $380,842 | +55.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lake Contractin… | #2 Allendale Grave… | #3 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0900064 | MEMBR WTRPR SYS B STR | 122 | SQ YD | $90.00 | $75.00 | $81.00 | |
| 2 | X2070302 | POROUS GRAN EMB SPEC | 800 | TON | $32.00 | $28.00 | $36.01 | |
| 3 | X2090210 | POROUS GRAN BACK SPEC | 47 | CU YD | $61.25 | $110.00 | $65.00 | |
| 4 | X2501000 | SEEDING CL 2 SPL | 0.1 | ACRE | $15,000.00 | $20,000.00 | $33,660.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 180 | CU YD | $16.00 | $52.00 | $15.30 | |
| 6 | 28100807 | STONE DUMP RIP CL A4 | 415 | TON | $39.00 | $41.00 | $69.80 | |
| 7 | 35101400 | AGG BASE CSE B | 165 | TON | $30.00 | $38.00 | $44.00 | |
| 8 | 50100100 | REM EXIST STRUCT | 1 | EACH | $6,000.00 | $18,000.00 | $26,596.00 | |
| 9 | 50800205 | REINF BARS, EPOXY CTD | 43,030 | POUND | $1.30 | $1.50 | $2.00 | |
| 10 | 50900205 | STEEL RAILING TY S1 | 59 | FOOT | $200.00 | $200.00 | $201.00 | |
| 11 | 51500100 | NAME PLATES | 1 | EACH | $350.00 | $400.00 | $507.00 | |
| 12 | 54003000 | CONC BOX CUL | 160.9 | CU YD | $585.00 | $800.00 | $928.44 | |
| 13 | 542D0223 | P CUL CL D 1 18 | 70 | FOOT | $35.00 | $45.00 | $55.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $9,000.00 | $18,000.00 | $18,360.00 | |
| 15 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $30.00 | $30.00 | $33.00 |