15-07131-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $728,011 | ||
| 2 | Allendale Gravel Co., Inc. | $786,773 | +8.1% | |
| 3 | Kieffer Bros. Construction Co., Inc. | $1,074,167 | +47.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 Allendale Grave… | #3 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $2,367.18 | $2,500.00 | $30,660.00 | |
| 2 | 20100110 | TREE REMOV 6-15 | 42 | UNIT | $31.85 | $20.00 | $60.00 | |
| 3 | 20100210 | TREE REMOV OVER 15 | 52 | UNIT | $37.16 | $20.00 | $60.00 | |
| 4 | 20100500 | TREE REMOV ACRES | 0.1 | ACRE | $10,617.50 | $10,000.00 | $44,100.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 304 | CU YD | $12.37 | $12.00 | $39.00 | |
| 6 | 20300100 | CHANNEL EXCAVATION | 240 | CU YD | $12.37 | $16.00 | $36.00 | |
| 7 | 20400800 | FURNISHED EXCAVATION | 1,146 | CU YD | $26.51 | $18.00 | $35.00 | |
| 8 | 20700110 | POROUS GRAN EMBANK | 239 | TON | $36.57 | $27.00 | $47.00 | |
| 9 | 28000400 | PERIMETER EROS BAR | 120 | FOOT | $5.50 | $8.00 | $6.00 | |
| 10 | 28100807 | STONE DUMP RIP CL A4 | 580 | TON | $40.66 | $34.00 | $60.00 | |
| 11 | 40200800 | AGG SURF CSE B | 351 | TON | $27.15 | $25.00 | $43.00 | |
| 12 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $13,651.65 | $10,000.00 | $44,362.00 | |
| 13 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $9,636.44 | $6,000.00 | $44,362.00 | |
| 14 | 50300225 | CONC STRUCT | 85.8 | CU YD | $1,277.35 | $800.00 | $1,050.00 | |
| 15 | 50300255 | CONC SUP-STR | 175.7 | CU YD | $1,251.90 | $1,845.00 | $1,440.00 | |
| 16 | 50300280 | CONCRETE ENCASEMENT | 19.1 | CU YD | $848.55 | $1,200.00 | $1,613.56 | |
| 17 | 50300300 | PROTECTIVE COAT | 481 | SQ YD | $2.70 | $3.00 | $3.00 | |
| 18 | 50800205 | REINF BARS, EPOXY CTD | 100,130 | POUND | $1.21 | $1.30 | $2.00 | |
| 19 | 50900205 | STEEL RAILING TY S1 | 259 | FOOT | $132.49 | $120.00 | $137.00 | |
| 20 | 51201400 | FUR STL PILE HP10X42 | 1,350 | FOOT | $41.28 | $30.00 | $25.00 | |
| 21 | 51202305 | DRIVING PILES | 1,350 | FOOT | $0.0200 | $1.00 | $43.00 | |
| 22 | 51203400 | TEST PILE ST HP10X42 | 4 | EACH | $3,202.20 | $12,000.00 | $7,644.00 | |
| 23 | 51500100 | NAME PLATES | 2 | EACH | $462.11 | $350.00 | $577.50 | |
| 24 | 542D0220 | P CUL CL D 1 15 | 72 | FOOT | $44.06 | $30.00 | $82.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $42,952.64 | $30,000.00 | $81,375.00 | |
| 26 | 72501000 | TERMINAL MARKER - DA | 8 | EACH | $31.85 | $30.00 | $46.00 |