15-11119-00-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Depew and Owen Builders, Inc. Low bidder | $458,888 | ||
| 2 | A. J. Walker Construction Company | $505,758 | +10.2% | |
| 3 | County Contractors, Inc. | $513,477 | +11.9% | |
| 4 | Kinney Contractors, Inc. | $574,879 | +25.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Depew and Owen … | #2 A. J. Walker Co… | #3 County Contract… | #4 Kinney Contract… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 20100500 | TREE REMOV ACRES | 0.1 | ACRE | $45,000.00 | $31,692.00 | $20,000.00 | $24,000.00 | |
| 2 | 20200100 | EARTH EXCAVATION | 1,248 | CU YD | $12.00 | $10.16 | $14.25 | $16.00 | |
| 3 | 20300100 | CHANNEL EXCAVATION | 1,519 | CU YD | $12.00 | $14.90 | $10.50 | $10.00 | |
| 4 | 20400800 | FURNISHED EXCAVATION | 1,346 | CU YD | $16.00 | $21.00 | $20.00 | $30.00 | |
| 5 | 25000200 | SEEDING CL 2 | 1 | ACRE | $2,207.00 | $2,206.80 | $2,330.00 | $2,200.00 | |
| 6 | 25000400 | NITROGEN FERT NUTR | 90 | POUND | $1.15 | $1.15 | $1.25 | $1.15 | |
| 7 | 25000500 | PHOSPHORUS FERT NUTR | 90 | POUND | $1.15 | $1.15 | $1.25 | $1.15 | |
| 8 | 25000600 | POTASSIUM FERT NUTR | 90 | POUND | $1.15 | $1.15 | $1.25 | $1.15 | |
| 9 | 25100115 | MULCH METHOD 2 | 1 | ACRE | $1,894.00 | $1,893.75 | $2,000.00 | $2,200.00 | |
| 10 | 28000250 | TEMP EROS CONTR SEED | 200 | POUND | $2.00 | $3.00 | $1.00 | $2.50 | |
| 11 | 28000305 | TEMP DITCH CHECKS | 21 | FOOT | $14.00 | $4.00 | $5.00 | $20.00 | |
| 12 | 28000500 | INLET & PIPE PROTECT | 2 | EACH | $150.00 | $175.00 | $50.00 | $170.00 | |
| 13 | 28100807 | STONE DUMP RIP CL A4 | 715 | TON | $42.00 | $57.53 | $60.00 | $55.00 | |
| 14 | 28200200 | FILTER FABRIC | 935 | SQ YD | $2.00 | $1.51 | $3.00 | $2.20 | |
| 15 | 40200800 | AGG SURF CSE B | 644 | TON | $28.00 | $23.79 | $20.00 | $30.00 | |
| 16 | 50100100 | REM EXIST STRUCT | 1 | EACH | $8,500.00 | $7,018.40 | $12,550.00 | $18,000.00 | |
| 17 | 50200100 | STRUCTURE EXCAVATION | 130 | CU YD | $12.00 | $17.67 | $12.75 | $21.00 | |
| 18 | 50300225 | CONC STRUCT | 111.4 | CU YD | $600.00 | $705.46 | $600.00 | $850.00 | |
| 19 | 50300280 | CONCRETE ENCASEMENT | 2.8 | CU YD | $650.00 | $525.81 | $1,275.00 | $600.00 | |
| 20 | 50400405 | P P CONC DK BM 21 DP | 2,598 | SQ FT | $66.00 | $69.21 | $70.00 | $78.00 | |
| 21 | 50800105 | REINFORCEMENT BARS | 9,400 | POUND | $1.25 | $1.59 | $1.55 | $2.00 | |
| 22 | 50900205 | STEEL RAILING TY S1 | 220 | FOOT | $106.00 | $101.15 | $107.00 | $110.00 | |
| 23 | 51201400 | FUR STL PILE HP10X42 | 288 | FOOT | $20.00 | $41.97 | $42.50 | $50.00 | |
| 24 | 51201600 | FUR STL PILE HP12X53 | 400 | FOOT | $34.00 | $41.74 | $48.00 | $52.00 | |
| 25 | 51202305 | DRIVING PILES | 688 | FOOT | $1.00 | $0.00 | $0.1000 | $0.1000 | |
| 26 | 51203400 | TEST PILE ST HP10X42 | 2 | EACH | $5,500.00 | $5,085.83 | $3,300.00 | $3,200.00 | |
| 27 | 51203600 | TEST PILE ST HP12X53 | 2 | EACH | $5,500.00 | $5,838.76 | $3,730.00 | $3,600.00 | |
| 28 | 51500100 | NAME PLATES | 1 | EACH | $350.00 | $400.00 | $550.00 | $500.00 | |
| 29 | 542D0220 | P CUL CL D 1 15 | 36 | FOOT | $32.00 | $32.25 | $31.00 | $31.00 | |
| 30 | 542D1075 | P CUL CL D 2 30 | 108 | FOOT | $50.00 | $36.78 | $48.00 | $36.00 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $9,942.50 | $13,000.00 | $30,000.00 | $13,000.00 | |
| 32 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $40.00 | $37.50 | $40.00 | $38.00 |