06-00058-00-FP
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Shores Builders, Inc. Low bidder | $652,388 | ||
| 2 | Kieffer Bros. Construction Co., Inc. | $729,986 | +11.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Shores Builders… | #2 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|
| 1 | XX004633 | FIELD TILE ADJUST | 3 | EACH | $104.27 | $1,350.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 7.4 | ACRE | $3,530.00 | $3,000.00 | |
| 3 | Z0068900 | STONE LINED DITCH | 67 | TON | $53.19 | $67.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 4,430 | CU YD | $1.70 | $17.70 | |
| 5 | 20400800 | FURNISHED EXCAVATION | 4,514 | CU YD | $19.31 | $20.00 | |
| 6 | 20900110 | POROUS GRAN BACKFILL | 96 | CU YD | $69.00 | $60.00 | |
| 7 | 28000305 | TEMP DITCH CHECKS | 525 | FOOT | $3.30 | $15.00 | |
| 8 | 28100807 | STONE DUMP RIP CL A4 | 598 | TON | $78.00 | $67.00 | |
| 9 | 35200300 | PROC SOIL-CEM BC 8 | 14,684 | SQ YD | $4.57 | $2.50 | |
| 10 | 35200500 | CEMENT | 7,929 | 100 WT | $9.86 | $9.00 | |
| 11 | 40200800 | AGG SURF CSE B | 299 | TON | $34.50 | $85.00 | |
| 12 | 40300200 | BIT MATLS PR CT | 19 | TON | $1,495.00 | $965.00 | |
| 13 | 40300400 | BIT MATLS C&S CT | 94 | TON | $920.00 | $690.00 | |
| 14 | 40300500 | COVER COAT AGG | 367 | TON | $57.50 | $40.50 | |
| 15 | 40300600 | SEAL COAT AGG | 184 | TON | $57.50 | $40.50 | |
| 16 | 50800105 | REINFORCEMENT BARS | 2,400 | POUND | $0.00 | $3.40 | |
| 17 | 54003000 | CONC BOX CUL | 30.8 | CU YD | $1,435.00 | $1,420.00 | |
| 18 | 54010905 | PCBC 9X5 | 88 | FOOT | $609.00 | $992.00 | |
| 19 | 542A5479 | P CUL CL A 1 EQRS 24 | 51 | FOOT | $94.00 | $200.00 | |
| 20 | 542D0235 | P CUL CL D 1 30 | 133 | FOOT | $74.00 | $173.00 | |
| 21 | 542D5485 | P CUL CL D 1 EQRS 30 | 53 | FOOT | $76.00 | $191.00 | |
| 22 | 542D5491 | P CUL CL D 1 EQRS 36 | 98 | FOOT | $84.00 | $222.00 | |
| 23 | 54214509 | PRC FL END S EQ RS 24 | 2 | EACH | $2,056.00 | $2,130.00 | |
| 24 | 59300100 | CONTR LOW-STRENG MATL | 13 | CU YD | $240.00 | $163.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $38,606.00 | $27,199.50 |