19-00088-01-BR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | County Contractors, Inc. Low bidder | $1,032,726 | ||
| 2 | Stark Excavating, Inc. | $1,121,697 | +8.6% | |
| 3 | William Charles Construction Company, LLC | $1,196,000 | +15.8% | |
| 4 | Otto Baum Company, Inc. | $1,470,000 | +42.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 County Contract… | #2 Stark Excavatin… | #3 William Charles… | #4 Otto Baum Compa… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X2010400 | STUMP REMOVAL ONLY | 198 | UNIT | $22.00 | $17.00 | $21.00 | $25.00 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 0.75 | ACRE | $8,000.00 | $6,000.00 | $6,995.00 | $4,912.65 | |
| 3 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $5,000.00 | $4,000.00 | $10,000.00 | $4,036.34 | |
| 4 | Z0001900 | ASB BEARING PAD REMOV | 32 | EACH | $63.00 | $35.00 | $128.00 | $30.79 | |
| 5 | Z0010400 | CLEANING BRIDGE SEATS | 325 | SQ FT | $7.00 | $5.00 | $16.00 | $13.57 | |
| 6 | Z0012754 | STR REP CON DP = < 5 | 73 | SQ FT | $320.00 | $295.00 | $520.00 | $800.00 | |
| 7 | Z0049790 | RELOC NAME PLATES | 1 | EACH | $200.00 | $225.00 | $750.00 | $1,260.54 | |
| 8 | 20200100 | EARTH EXCAVATION | 250 | CU YD | $28.00 | $80.00 | $100.00 | $99.04 | |
| 9 | 20300100 | CHANNEL EXCAVATION | 541 | CU YD | $17.00 | $30.00 | $80.00 | $61.40 | |
| 10 | 28100807 | STONE DUMP RIP CL A4 | 563 | TON | $114.00 | $130.00 | $80.00 | $115.59 | |
| 11 | 28200200 | FILTER FABRIC | 732 | SQ YD | $4.50 | $4.25 | $6.00 | $6.86 | |
| 12 | 35100100 | AGG BASE CSE A | 15 | TON | $75.00 | $150.00 | $155.00 | $183.95 | |
| 13 | 40600290 | BIT MATLS TACK CT | 436 | POUND | $1.30 | $1.25 | $1.22 | $1.30 | |
| 14 | 40600982 | HMA SURF REM BUTT JT | 269 | SQ YD | $15.75 | $15.00 | $14.78 | $15.70 | |
| 15 | 40604000 | HMA SC IL-9.5FG C N50 | 190 | TON | $210.00 | $210.00 | $200.41 | $212.87 | |
| 16 | 48101500 | AGGREGATE SHLDS B 6 | 134 | SQ YD | $41.00 | $60.00 | $30.00 | $44.22 | |
| 17 | 50101700 | REM EXIST SUP-STR N1 | 1 | EACH | $80,500.00 | $65,000.00 | $72,532.88 | $250,000.00 | |
| 18 | 50200100 | STRUCTURE EXCAVATION | 13 | CU YD | $35.00 | $85.00 | $100.00 | $279.46 | |
| 19 | 50300225 | CONC STRUCT | 3.2 | CU YD | $1,725.00 | $2,250.00 | $2,900.00 | $5,540.93 | |
| 20 | 50400505 | P P CONC DK BM 27 DP | 5,376 | SQ FT | $106.50 | $120.00 | $125.00 | $130.00 | |
| 21 | 50800105 | REINFORCEMENT BARS | 280 | POUND | $10.00 | $19.00 | $15.00 | $21.75 | |
| 22 | 50900205 | STEEL RAILING TY S1 | 452 | FOOT | $161.50 | $160.00 | $154.15 | $162.62 | |
| 23 | 51500100 | NAME PLATES | 1 | EACH | $750.00 | $750.00 | $1,100.00 | $1,951.27 | |
| 24 | 58100200 | WATERPRF MEMBRANE SYS | 602 | SQ YD | $43.00 | $45.00 | $45.00 | $43.03 | |
| 25 | 59000200 | EPOXY CRACK INJECTION | 13 | FOOT | $135.00 | $80.00 | $90.00 | $76.31 | |
| 26 | 59300100 | CONTR LOW-STRENG MATL | 11.6 | CU YD | $295.00 | $180.00 | $285.00 | $558.09 | |
| 27 | 63000001 | SPBGR TY A 6FT POSTS | 87.5 | FOOT | $33.75 | $32.00 | $31.95 | $33.94 | |
| 28 | 63100075 | TRAF BAR TERM T5A | 4 | EACH | $1,620.00 | $1,550.00 | $1,535.00 | $1,630.47 | |
| 29 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,865.00 | $3,750.00 | $3,660.00 | $3,887.63 | |
| 30 | 63200310 | GUARDRAIL REMOV | 256 | FOOT | $7.00 | $7.00 | $21.55 | $39.28 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $61,000.00 | $65,000.00 | $71,000.00 | $89,807.21 | |
| 32 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $52.00 | $50.00 | $50.00 | $53.11 |