16-00123-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $1,048,500 | ||
| 2 | County Contractors, Inc. | $1,132,887 | +8.0% | |
| 3 | Plocher Construction Company, Inc. | $1,331,200 | +27.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 County Contract… | #3 Plocher Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.5 | ACRE | $10,008.26 | $9,650.00 | $9,420.00 | |
| 2 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,090.42 | $4,500.00 | $20,000.00 | |
| 3 | Z0001900 | ASB BEARING PAD REMOV | 56 | EACH | $29.05 | $48.00 | $60.00 | |
| 4 | Z0010400 | CLEANING BRIDGE SEATS | 440 | SQ FT | $9.31 | $4.50 | $4.50 | |
| 5 | Z0012754 | STR REP CON DP = < 5 | 91 | SQ FT | $373.72 | $315.00 | $270.00 | |
| 6 | Z0049790 | RELOC NAME PLATES | 1 | EACH | $138.84 | $175.00 | $150.00 | |
| 7 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 9 | 20200100 | EARTH EXCAVATION | 17 | CU YD | $101.63 | $40.00 | $60.00 | |
| 10 | 20300100 | CHANNEL EXCAVATION | 182 | CU YD | $24.70 | $31.00 | $60.00 | |
| 11 | 20400800 | FURNISHED EXCAVATION | 190 | CU YD | $79.95 | $10.00 | $60.00 | |
| 12 | 28100807 | STONE DUMP RIP CL A4 | 454 | TON | $92.84 | $117.00 | $80.00 | |
| 13 | 28200200 | FILTER FABRIC | 541 | SQ YD | $2.68 | $4.50 | $3.10 | |
| 14 | 35100100 | AGG BASE CSE A | 12 | TON | $170.88 | $85.00 | $180.00 | |
| 15 | 40600290 | BIT MATLS TACK CT | 572 | POUND | $5.42 | $4.30 | $4.10 | |
| 16 | 40600982 | HMA SURF REM BUTT JT | 297 | SQ YD | $25.13 | $19.75 | $19.65 | |
| 17 | 40604000 | HMA SC IL-9.5FG C N50 | 266 | TON | $218.60 | $195.00 | $195.75 | |
| 18 | 48101500 | AGGREGATE SHLDS B 6 | 314 | SQ YD | $21.13 | $28.00 | $21.00 | |
| 19 | 50101700 | REM EXIST SUP-STR N1 | 1 | EACH | $50,000.00 | $79,000.00 | $194,000.00 | |
| 20 | 50102400 | CONC REM | 3.5 | CU YD | $3,898.01 | $5,735.00 | $6,300.00 | |
| 21 | 50200100 | STRUCTURE EXCAVATION | 25 | CU YD | $99.06 | $23.00 | $60.00 | |
| 22 | 50300225 | CONC STRUCT | 14.3 | CU YD | $2,089.37 | $3,900.00 | $2,650.00 | |
| 23 | 50400305 | P P CONC DK BM 17 DP | 6,000 | SQ FT | $90.20 | $94.75 | $105.00 | |
| 24 | 50800105 | REINFORCEMENT BARS | 1,770 | POUND | $2.17 | $10.00 | $7.00 | |
| 25 | 50800205 | REINF BARS, EPOXY CTD | 640 | POUND | $3.99 | $4.00 | $4.00 | |
| 26 | 50900205 | STEEL RAILING TY S1 | 404 | FOOT | $159.31 | $165.00 | $177.25 | |
| 27 | 51500100 | NAME PLATES | 1 | EACH | $752.01 | $650.00 | $703.65 | |
| 28 | 52000110 | PREF JT STRIP SEAL | 60 | FOOT | $230.63 | $225.00 | $260.00 | |
| 29 | 58100200 | WATERPRF MEMBRANE SYS | 673 | SQ YD | $42.31 | $40.00 | $40.00 | |
| 30 | 59300100 | CONTR LOW-STRENG MATL | 6.7 | CU YD | $220.14 | $265.00 | $635.00 | |
| 31 | 63000001 | SPBGR TY A 6FT POSTS | 200 | FOOT | $41.97 | $43.00 | $37.50 | |
| 32 | 63100075 | TRAF BAR TERM T5A | 4 | EACH | $2,629.56 | $1,830.00 | $1,250.00 | |
| 33 | 63100167 | TR BAR TRM T1 SPL TAN | 3 | EACH | $4,196.67 | $4,185.00 | $3,600.00 | |
| 34 | 63200310 | GUARDRAIL REMOV | 152 | FOOT | $16.29 | $7.00 | $15.00 | |
| 35 | 67100100 | MOBILIZATION | 1 | L SUM | $62,594.87 | $65,000.00 | $93,000.00 | |
| 36 | 72501000 | TERMINAL MARKER - DA | 3 | EACH | $53.12 | $50.00 | $42.00 |