18-00221-00-GR
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Clevenger Contractors, Inc. Low bidder | $873,855 | ||
| 2 | Lovewell Fencing, Inc. | $935,095 | +7.0% | |
| 3 | Midwest Fence Corporation | $949,820 | +8.7% | |
| 4 | COLLINS & HERMANN, INC. | $1,086,610 | +24.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Clevenger Contr… | #2 Lovewell Fencin… | #3 Midwest Fence C… | #4 COLLINS & HERMA… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0326519 | STEEL RAILING REMOVAL | 386 | FOOT | $12.40 | $10.00 | $10.00 | $28.96 | |
| 2 | X2501000 | SEEDING CL 2 SPL | 1 | ACRE | $4,840.00 | $4,700.00 | $10,500.00 | $16,996.70 | |
| 3 | X6300130 | SPBGR TY A SPL | 386 | FOOT | $27.95 | $16.00 | $25.00 | $20.32 | |
| 4 | X6300210 | GUARDRAIL BLOCKS | 55 | EACH | $102.00 | $15.00 | $60.00 | $20.41 | |
| 5 | X6330725 | SPBGR (SHORT RADIUS) | 287.5 | FOOT | $61.70 | $75.00 | $70.00 | $50.51 | |
| 6 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 7 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 8 | 20400800 | FURNISHED EXCAVATION | 1,190 | CU YD | $57.70 | $56.00 | $75.00 | $51.34 | |
| 9 | 28000250 | TEMP EROS CONTR SEED | 100 | POUND | $5.15 | $5.00 | $2.00 | $14.38 | |
| 10 | 63000001 | SPBGR TY A 6FT POSTS | 3,350 | FOOT | $23.05 | $29.00 | $25.00 | $21.93 | |
| 11 | 63000003 | SPBGR TY A 9FT POSTS | 5,587.5 | FOOT | $28.15 | $36.00 | $30.00 | $27.83 | |
| 12 | 63000007 | SPBGR TY B 6FT POSTS | 100 | FOOT | $38.85 | $40.00 | $40.00 | $39.05 | |
| 13 | 63000009 | SPBGR TY B 9FT POSTS | 225 | FOOT | $47.10 | $50.00 | $50.00 | $46.11 | |
| 14 | 63000350 | LSG OV CUL 12'6" SPAN | 150 | FOOT | $29.75 | $29.00 | $45.00 | $26.14 | |
| 15 | 63000360 | LSG OV CUL 18'9" SPAN | 87.5 | FOOT | $30.20 | $29.00 | $45.00 | $24.86 | |
| 16 | 63100045 | TRAF BAR TERM T2 | 2 | EACH | $1,280.00 | $1,350.00 | $2,000.00 | $1,041.88 | |
| 17 | 63100070 | TRAF BAR TERM T5 | 1 | EACH | $1,040.00 | $1,000.00 | $1,500.00 | $1,090.33 | |
| 18 | 63100075 | TRAF BAR TERM T5A | 40 | EACH | $1,210.00 | $1,100.00 | $1,200.00 | $1,043.04 | |
| 19 | 63100167 | TR BAR TRM T1 SPL TAN | 107 | EACH | $2,772.20 | $2,700.00 | $3,000.00 | $3,205.24 | |
| 20 | 63200310 | GUARDRAIL REMOV | 12,825 | FOOT | $7.40 | $6.50 | $6.25 | $5.23 | |
| 21 | 67100100 | MOBILIZATION | 1 | L SUM | $37,975.25 | $52,000.00 | $49,000.00 | $53,627.75 | |
| 22 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $8,456.00 | $25,000.00 | $18,000.00 | $203,088.27 | |
| 23 | 72501000 | TERMINAL MARKER - DA | 107 | EACH | $35.00 | $25.00 | $30.00 | $23.24 | |
| 24 | 78200005 | GRDRAIL REF TYPE A | 357 | EACH | $9.00 | $8.00 | $8.00 | $2.91 |