16-00054-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $910,055 | ||
| 2 | C-Hill Civil Contractors, Inc. | $1,298,983 | +42.7% | |
| 3 | William Charles Construction Company, LLC | $1,375,000 | +51.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 C-Hill Civil Co… | #3 William Charles… |
|---|---|---|---|---|---|---|---|---|
| 1 | XX008340 | TIMBER BRDGE APP RAIL | 300 | FOOT | $101.28 | $105.00 | $110.00 | |
| 2 | X0322508 | PED TRUSS SUPERSTR | 2,000 | SQ FT | $242.76 | $310.00 | $285.00 | |
| 3 | X2020410 | EARTH EXCAVATION SPL | 300 | CU YD | $51.97 | $110.00 | $100.00 | |
| 4 | X2501000 | SEEDING CL 2 SPL | 0.4 | ACRE | $11,952.93 | $12,000.00 | $11,300.00 | |
| 5 | X4400196 | HMA SURF REM SPL | 185 | SQ YD | $21.83 | $15.00 | $13.00 | |
| 6 | X4811300 | AGGREGATE SHLDS B SPL | 11 | TON | $104.76 | $286.00 | $250.00 | |
| 7 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $9,673.43 | $20,000.00 | $25,000.00 | |
| 8 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $8,361.45 | $20,000.00 | $11,250.00 | |
| 9 | Z0015500 | DEBRIS REMOVAL | 1 | L SUM | $12,756.06 | $40,000.00 | $5,000.00 | |
| 10 | Z0022810 | FENCE REMOVAL SPECIAL | 300 | FOOT | $18.30 | $15.00 | $30.00 | |
| 11 | Z0064600 | SELECTIVE CLEARING | 0.04 | ACRE | $69,915.50 | $155,000.00 | $100,000.00 | |
| 12 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 13 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 14 | 20100110 | TREE REMOV 6-15 | 93 | UNIT | $69.95 | $55.00 | $125.00 | |
| 15 | 20100210 | TREE REMOV OVER 15 | 134 | UNIT | $69.92 | $65.00 | $175.00 | |
| 16 | 20300100 | CHANNEL EXCAVATION | 79 | CU YD | $61.66 | $60.00 | $60.00 | |
| 17 | 28000250 | TEMP EROS CONTR SEED | 20 | POUND | $7.93 | $0.0100 | $12.00 | |
| 18 | 28000400 | PERIMETER EROS BAR | 475 | FOOT | $6.91 | $4.00 | $8.00 | |
| 19 | 28100107 | STONE RIPRAP CL A4 | 798 | SQ YD | $70.77 | $88.00 | $120.00 | |
| 20 | 28200200 | FILTER FABRIC | 798 | SQ YD | $4.76 | $3.00 | $5.00 | |
| 21 | 35800100 | PREPARATION OF BASE | 146 | SQ YD | $12.86 | $17.00 | $25.00 | |
| 22 | 35800200 | AGG BASE REPAIR | 5 | TON | $85.08 | $40.00 | $250.00 | |
| 23 | 40201000 | AGGREGATE-TEMP ACCESS | 200 | TON | $61.19 | $88.00 | $85.00 | |
| 24 | 40600275 | BIT MATLS PR CT | 38 | POUND | $16.13 | $16.00 | $15.25 | |
| 25 | 40604050 | HMA SC IL-9.5 C N50 | 16 | TON | $1,054.63 | $1,050.00 | $997.02 | |
| 26 | 50100100 | REM EXIST STRUCT | 1 | EACH | $66,995.07 | $105,000.00 | $307,862.18 | |
| 27 | 50200100 | STRUCTURE EXCAVATION | 95 | CU YD | $36.85 | $55.00 | $75.00 | |
| 28 | 50300225 | CONC STRUCT | 15.2 | CU YD | $1,846.48 | $2,000.00 | $1,700.00 | |
| 29 | 50300300 | PROTECTIVE COAT | 28.2 | SQ YD | $5.52 | $8.00 | $15.00 | |
| 30 | 50301350 | CONC SUPSTR APP SLAB | 9.4 | CU YD | $1,024.83 | $1,000.00 | $1,000.00 | |
| 31 | 50800205 | REINF BARS, EPOXY CTD | 3,760 | POUND | $2.50 | $3.00 | $3.00 | |
| 32 | 51201600 | FUR STL PILE HP12X53 | 120 | FOOT | $149.32 | $53.00 | $60.00 | |
| 33 | 51202305 | DRIVING PILES | 120 | FOOT | $0.0200 | $0.0100 | $125.00 | |
| 34 | 51203600 | TEST PILE ST HP12X53 | 2 | EACH | $3,691.08 | $35,000.00 | $7,000.00 | |
| 35 | 51500100 | NAME PLATES | 1 | EACH | $701.12 | $500.00 | $1,000.00 | |
| 36 | 52100520 | ANCHOR BOLTS 1 | 8 | EACH | $215.88 | $110.00 | $150.00 | |
| 37 | 58600101 | GRANULAR BACKFILL STR | 43 | CU YD | $119.40 | $115.00 | $100.00 | |
| 38 | 58700300 | CONCRETE SEALER | 336 | SQ FT | $2.42 | $2.00 | $3.00 | |
| 39 | 67100100 | MOBILIZATION | 1 | L SUM | $53,693.26 | $129,500.00 | $82,500.00 |