19-00056-07-PV
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $2,166,705 | ||
| 2 | P. H. Broughton & Sons, Inc. and Perry Broughton Trucking and Excavating, Inc. | $2,301,298 | +6.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 P. H. Broughton… |
|---|---|---|---|---|---|---|---|
| 1 | X0327112 | STUMP REMOVAL ACRES | 0.75 | ACRE | $37,888.92 | $67,825.00 | |
| 2 | X0327301 | RELOCATE EX MAILBOX | 10 | EACH | $997.91 | $418.03 | |
| 3 | X2501000 | SEEDING CL 2 SPL | 10.5 | ACRE | $2,157.75 | $2,586.82 | |
| 4 | X6061460 | PAVED DITCH SPEC | 22 | FOOT | $220.54 | $230.84 | |
| 5 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $17,403.44 | $15,510.19 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $9,569.21 | $13,148.77 | |
| 7 | Z0023602 | GRAN CULVERT BACKFILL | 1,824 | CU YD | $100.80 | $76.15 | |
| 8 | Z0041500 | PLUG EX CULVERTS | 2 | EACH | $1,766.62 | $4,187.00 | |
| 9 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | |
| 10 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 6,596 | CU YD | $11.70 | $12.57 | |
| 12 | 20400800 | FURNISHED EXCAVATION | 23,631 | CU YD | $23.67 | $41.54 | |
| 13 | 28000250 | TEMP EROS CONTR SEED | 1,050 | POUND | $5.41 | $4.80 | |
| 14 | 28000305 | TEMP DITCH CHECKS | 325 | FOOT | $81.90 | $11.87 | |
| 15 | 28000400 | PERIMETER EROS BAR | 5,985 | FOOT | $3.95 | $5.03 | |
| 16 | 28000500 | INLET & PIPE PROTECT | 12 | EACH | $435.89 | $300.00 | |
| 17 | 28300400 | AGGREGATE DITCH | 1,245 | TON | $93.20 | $48.68 | |
| 18 | 35100100 | AGG BASE CSE A | 348 | TON | $59.55 | $45.67 | |
| 19 | 35600700 | HMA BC WID 6 | 3,225 | SQ YD | $32.54 | $37.68 | |
| 20 | 40600275 | BIT MATLS PR CT | 1,164 | POUND | $1.94 | $0.6700 | |
| 21 | 40600290 | BIT MATLS TACK CT | 9,371 | POUND | $1.14 | $0.5500 | |
| 22 | 40600982 | HMA SURF REM BUTT JT | 305 | SQ YD | $43.83 | $21.65 | |
| 23 | 40603080 | HMA BC IL-19.0 N50 | 2,430 | TON | $89.51 | $89.66 | |
| 24 | 40604050 | HMA SC IL-9.5 C N50 | 1,712 | TON | $103.64 | $94.58 | |
| 25 | 44000100 | PAVEMENT REM | 1,083 | SQ YD | $51.88 | $9.94 | |
| 26 | 48100100 | AGGREGATE SHLDS A | 3,375 | TON | $30.45 | $31.13 | |
| 27 | 50105220 | PIPE CULVERT REMOV | 562 | FOOT | $45.68 | $15.79 | |
| 28 | 542A0229 | P CUL CL A 1 24 | 32 | FOOT | $100.26 | $90.14 | |
| 29 | 542A1909 | P CUL CL A 3 24 | 388 | FOOT | $210.17 | $81.82 | |
| 30 | 542A3391 | P CUL CL A 5 36 | 204 | FOOT | $209.64 | $132.50 | |
| 31 | 542D0220 | P CUL CL D 1 15 | 108 | FOOT | $32.51 | $80.11 | |
| 32 | 542D0223 | P CUL CL D 1 18 | 38 | FOOT | $41.97 | $98.76 | |
| 33 | 542D0229 | P CUL CL D 1 24 | 44 | FOOT | $54.37 | $116.50 | |
| 34 | 542D1060 | P CUL CL D 2 15 | 30 | FOOT | $19.94 | $80.11 | |
| 35 | 542D1063 | P CUL CL D 2 18 | 56 | FOOT | $42.72 | $98.76 | |
| 36 | 54213669 | PRC FLAR END SEC 24 | 8 | EACH | $1,636.09 | $1,300.00 | |
| 37 | 54213681 | PRC FLAR END SEC 36 | 2 | EACH | $1,903.54 | $2,306.33 | |
| 38 | 54262715 | METAL FL END SEC 15" | 8 | EACH | $585.24 | $430.10 | |
| 39 | 54262718 | METAL FL END SEC 18" | 4 | EACH | $585.24 | $688.28 | |
| 40 | 54262724 | METAL FL END SEC 24" | 2 | EACH | $797.38 | $1,029.54 | |
| 41 | 59300100 | CONTR LOW-STRENG MATL | 290 | CU YD | $199.39 | $182.83 | |
| 42 | 66600105 | FUR ERECT ROW MARKERS | 40 | EACH | $275.70 | $201.41 | |
| 43 | 67100100 | MOBILIZATION | 1 | L SUM | $78,649.03 | $14,045.25 | |
| 44 | 70107025 | CHANGEABLE MESSAGE SN | 150 | CAL DA | $65.63 | $67.09 | |
| 45 | 78001110 | PAINT PVT MK LINE 4 | 15,530 | FOOT | $0.2900 | $0.2900 |