14-00096-00-PP
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $1,085,681 | ||
| 2 | Diamond Construction Company | $1,104,761 | +1.8% | |
| 3 | K. E. Vas Company | $1,206,021 | +11.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 Diamond Constru… | #3 K. E. Vas Compa… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327980 | PAVMT MRKG REM WTR BL | 30,846 | SQ FT | $0.0100 | $1.13 | $1.03 | |
| 2 | X4401198 | HMA SURF REM VAR DP | 67,910 | SQ YD | $2.14 | $1.00 | $1.00 | |
| 3 | X4811800 | AGGREGATE SHLDS SPL | 17,894 | SQ YD | $3.26 | $2.50 | $6.00 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $7,753.43 | $12,000.00 | $20,000.00 | |
| 5 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 6 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 7 | 40600290 | BIT MATLS TACK CT | 45,815 | POUND | $1.75 | $1.45 | $1.00 | |
| 8 | 40600625 | LEV BIND MM N50 | 2,495 | TON | $86.63 | $95.00 | $100.00 | |
| 9 | 40600990 | TEMPORARY RAMP | 17 | SQ YD | $30.03 | $0.0100 | $10.00 | |
| 10 | 40603310 | HMA SC "C" N50 | 5,543 | TON | $84.69 | $92.00 | $101.00 | |
| 11 | 40800050 | INCIDENTAL HMA SURF | 420 | TON | $176.18 | $200.00 | $164.00 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $6,778.54 | $15,500.00 | $20,000.00 | |
| 13 | 70300100 | SHORT TERM PAVT MKING | 2,440 | FOOT | $0.9100 | $0.2500 | $1.00 | |
| 14 | 70300150 | SHRT TRM PAVT MK REM | 814 | SQ FT | $4.72 | $2.00 | $5.00 | |
| 15 | 70300220 | TEMP PVT MK LINE 4 | 92,536 | FOOT | $0.0100 | $0.1200 | $0.1100 | |
| 16 | 78001110 | PAINT PVT MK LINE 4 | 92,536 | FOOT | $0.1300 | $0.1200 | $0.1100 |