22-03123-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | C-Hill Civil Contractors, Inc. Low bidder | $361,888 | ||
| 2 | White Construction LLC | $401,474 | +10.9% | |
| 3 | Stark Excavating, Inc. | $405,685 | +12.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 C-Hill Civil Co… | #2 White Construct… | #3 Stark Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.25 | ACRE | $12,000.00 | $16,500.00 | $15,500.00 | |
| 2 | X5060601 | C&D N-LEAD PT C RS N1 | 1 | L SUM | $1,100.00 | $2,000.00 | $1,050.00 | |
| 3 | X6110073 | EXIST FIELD TILE REM | 160 | FOOT | $25.00 | $25.00 | $25.00 | |
| 4 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,500.00 | $5,000.00 | $4,000.00 | |
| 5 | Z0010501 | CLEAN & PT STL BR N1 | 1 | L SUM | $18,700.00 | $20,000.00 | $38,000.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 8 | CU YD | $275.00 | $350.00 | $185.00 | |
| 7 | 20300100 | CHANNEL EXCAVATION | 8 | CU YD | $150.00 | $350.00 | $55.00 | |
| 8 | 28100107 | STONE RIPRAP CL A4 | 80 | SQ YD | $80.00 | $120.00 | $175.00 | |
| 9 | 28200200 | FILTER FABRIC | 80 | SQ YD | $15.00 | $15.00 | $1.80 | |
| 10 | 35101400 | AGG BASE CSE B | 30 | TON | $120.00 | $100.00 | $150.00 | |
| 11 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $22,500.00 | $22,000.00 | $33,500.00 | |
| 12 | 50102400 | CONC REM | 0.2 | CU YD | $35,000.00 | $15,000.00 | $12,000.00 | |
| 13 | 50200100 | STRUCTURE EXCAVATION | 19.4 | CU YD | $150.00 | $140.00 | $135.00 | |
| 14 | 50300225 | CONC STRUCT | 6.5 | CU YD | $4,800.00 | $2,100.00 | $3,200.00 | |
| 15 | 50400305 | P P CONC DK BM 17 DP | 1,717 | SQ FT | $105.00 | $120.00 | $116.00 | |
| 16 | 50800205 | REINF BARS, EPOXY CTD | 870 | POUND | $5.00 | $5.00 | $9.00 | |
| 17 | 50900205 | STEEL RAILING TY S1 | 127 | FOOT | $171.00 | $162.70 | $170.00 | |
| 18 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $500.00 | $700.00 | |
| 19 | 59300100 | CONTR LOW-STRENG MATL | 44 | CU YD | $175.00 | $150.00 | $125.00 | |
| 20 | 60100060 | CONC HDWL FOR P DRAIN | 8 | EACH | $650.00 | $2,150.00 | $675.00 | |
| 21 | 60103400 | PIPE DRAINS CS 10 | 20 | FOOT | $98.50 | $145.00 | $63.00 | |
| 22 | 60103600 | PIPE DRAINS CS 15 | 20 | FOOT | $105.00 | $158.00 | $70.00 | |
| 23 | 60103700 | PIPE DRAINS CS 18 | 20 | FOOT | $112.50 | $170.00 | $80.00 | |
| 24 | 60103800 | PIPE DRAINS CS 21 | 20 | FOOT | $115.00 | $182.00 | $86.00 | |
| 25 | 60103900 | PIPE DRAINS CS 24 | 20 | FOOT | $121.00 | $192.00 | $90.00 | |
| 26 | 60104000 | PIPE DRAINS CS 27 | 20 | FOOT | $125.00 | $225.00 | $119.00 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $18,886.00 | $28,600.00 | $24,325.00 | |
| 28 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $47.50 | $50.00 |