22-03122-00-BR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | C-Hill Civil Contractors, Inc. Low bidder | $333,888 | ||
| 2 | Stark Excavating, Inc. | $382,947 | +14.7% | |
| 3 | White Construction LLC | $383,473 | +14.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 C-Hill Civil Co… | #2 Stark Excavatin… | #3 White Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.25 | ACRE | $12,000.00 | $15,500.00 | $16,500.00 | |
| 2 | X6110073 | EXIST FIELD TILE REM | 40 | FOOT | $25.00 | $25.00 | $28.00 | |
| 3 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,500.00 | $4,000.00 | $4,200.00 | |
| 4 | 20200100 | EARTH EXCAVATION | 8 | CU YD | $275.00 | $185.00 | $600.00 | |
| 5 | 28100107 | STONE RIPRAP CL A4 | 83 | SQ YD | $72.50 | $250.00 | $150.00 | |
| 6 | 28200200 | FILTER FABRIC | 83 | SQ YD | $15.00 | $1.80 | $15.00 | |
| 7 | 35101400 | AGG BASE CSE B | 18 | TON | $110.00 | $170.00 | $235.00 | |
| 8 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $22,500.00 | $28,000.00 | $22,000.00 | |
| 9 | 50102400 | CONC REM | 0.6 | CU YD | $11,250.00 | $6,500.00 | $10,000.00 | |
| 10 | 50200100 | STRUCTURE EXCAVATION | 19.6 | CU YD | $150.00 | $130.00 | $180.00 | |
| 11 | 50300225 | CONC STRUCT | 4.6 | CU YD | $4,800.00 | $5,500.00 | $2,500.00 | |
| 12 | 50400305 | P P CONC DK BM 17 DP | 1,953 | SQ FT | $103.00 | $115.00 | $125.00 | |
| 13 | 50800205 | REINF BARS, EPOXY CTD | 650 | POUND | $5.00 | $11.00 | $7.00 | |
| 14 | 50900205 | STEEL RAILING TY S1 | 145 | FOOT | $157.50 | $160.00 | $150.00 | |
| 15 | 51500100 | NAME PLATES | 1 | EACH | $500.00 | $700.00 | $500.00 | |
| 16 | 59300100 | CONTR LOW-STRENG MATL | 41.8 | CU YD | $170.00 | $125.00 | $200.00 | |
| 17 | 60100060 | CONC HDWL FOR P DRAIN | 2 | EACH | $1,200.00 | $650.00 | $2,500.00 | |
| 18 | 60103600 | PIPE DRAINS CS 15 | 20 | FOOT | $106.00 | $80.00 | $210.00 | |
| 19 | 60103700 | PIPE DRAINS CS 18 | 20 | FOOT | $115.00 | $97.00 | $230.00 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $17,803.00 | $22,975.00 | $15,000.00 | |
| 21 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $50.00 | $47.50 |