20-00056-11-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Rowe Construction, a div of UCM, Inc. Low bidder | $1,305,243 | ||
| 2 | H. J. Eppel & Co. | $1,373,160 | +5.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Rowe Constructi… | #2 H. J. Eppel & C… |
|---|---|---|---|---|---|---|---|
| 1 | LR400005 | CIR-FDR EMULS ASPHALT | 46,464 | GALLON | $2.20 | $2.10 | |
| 2 | LR400740 | CIP RECYCLING 4.0 | 33,237 | SQ YD | $4.18 | $4.00 | |
| 3 | LR403300 | SURFACE PROFILE MILL | 33,237 | SQ YD | $1.25 | $1.45 | |
| 4 | LR631020 | TRAF BAR TERM T1 | 12 | EACH | $2,183.50 | $2,084.00 | |
| 5 | X4401198 | HMA SURF REM VAR DP | 600 | SQ YD | $34.95 | $5.95 | |
| 6 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $75,000.00 | $82,000.00 | |
| 7 | Z0055300 | RUMBLE STRIP | 12 | EACH | $673.11 | $787.00 | |
| 8 | 30201700 | PORTLAND CEMENT | 110 | TON | $194.81 | $185.00 | |
| 9 | 40600290 | BIT MATLS TACK CT | 17,844 | POUND | $1.35 | $1.05 | |
| 10 | 40600990 | TEMPORARY RAMP | 122 | SQ YD | $40.22 | $16.00 | |
| 11 | 40602965 | HMA BC IL-9.5FG N50 | 2,450 | TON | $95.00 | $110.00 | |
| 12 | 40604050 | HMA SC IL-9.5 C N50 | 3,375 | TON | $95.00 | $108.00 | |
| 13 | 40800029 | BIT MATLS TACK CT | 1,000 | POUND | $2.15 | $1.05 | |
| 14 | 40800050 | INCIDENTAL HMA SURF | 350 | TON | $190.00 | $210.00 | |
| 15 | 44000155 | HMA SURF REM 1 1/2 | 6,625 | SQ YD | $5.31 | $3.80 | |
| 16 | 44000300 | CURB REM | 580 | FOOT | $35.17 | $12.50 | |
| 17 | 48102100 | AGG WEDGE SHLD TYPE B | 3,830 | TON | $0.0100 | $27.50 | |
| 18 | 60609800 | COMB CC&G TM6.18 | 580 | FOOT | $88.77 | $45.00 | |
| 19 | 63000001 | SPBGR TY A 6FT POSTS | 990 | FOOT | $30.31 | $28.90 | |
| 20 | 67100100 | MOBILIZATION | 1 | L SUM | $75,000.00 | $25,000.00 | |
| 21 | 78100100 | RAISED REFL PAVT MKR | 202 | EACH | $38.30 | $36.50 |