16-00444-00-SP
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Midwest Fence Corporation Low bidder | $1,958,373 | ||
| 2 | COLLINS & HERMANN, INC. | $2,064,915 | +5.4% | |
| 3 | Lovewell Fencing, Inc. | $2,574,899 | +31.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Midwest Fence C… | #2 COLLINS & HERMA… | #3 Lovewell Fencin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 4.75 | ACRE | $5,200.00 | $4,769.95 | $4,500.00 | |
| 2 | X6330725 | SPBGR (SHORT RADIUS) | 225 | FOOT | $45.00 | $56.76 | $50.00 | |
| 3 | X6331007 | REM/REP SPBGR RL ELEM | 450 | FOOT | $20.00 | $18.54 | $20.00 | |
| 4 | 20400800 | FURNISHED EXCAVATION | 5,280 | CU YD | $46.00 | $41.86 | $160.00 | |
| 5 | 21400100 | GRADING & SHAP DITCH | 1,377 | FOOT | $7.00 | $6.06 | $30.00 | |
| 6 | 25100630 | EROSION CONTR BLANKET | 2,258 | SQ YD | $5.00 | $3.84 | $4.00 | |
| 7 | 28000250 | TEMP EROS CONTR SEED | 500 | POUND | $8.00 | $7.62 | $18.00 | |
| 8 | 28000305 | TEMP DITCH CHECKS | 152 | FOOT | $19.00 | $16.83 | $20.00 | |
| 9 | 28000400 | PERIMETER EROS BAR | 20,447 | FOOT | $3.25 | $2.94 | $5.00 | |
| 10 | 28000500 | INLET & PIPE PROTECT | 27 | EACH | $175.00 | $161.37 | $400.00 | |
| 11 | 44004000 | PAVED DITCH REMOVAL | 105 | FOOT | $16.00 | $14.32 | $50.00 | |
| 12 | 48203021 | HMA SHOULDERS 6 | 36 | SQ YD | $166.00 | $152.23 | $250.00 | |
| 13 | 50105220 | PIPE CULVERT REMOV | 68 | FOOT | $45.00 | $40.60 | $50.00 | |
| 14 | 54002020 | EXPAN BOLTS 3/4 | 8 | EACH | $50.00 | $42.22 | $100.00 | |
| 15 | 542D0220 | P CUL CL D 1 15 | 488 | FOOT | $33.00 | $30.45 | $60.00 | |
| 16 | 542D0223 | P CUL CL D 1 18 | 752 | FOOT | $37.00 | $33.90 | $70.00 | |
| 17 | 542D0229 | P CUL CL D 1 24 | 212 | FOOT | $39.00 | $35.32 | $80.00 | |
| 18 | 542D0235 | P CUL CL D 1 30 | 16 | FOOT | $49.00 | $44.89 | $100.00 | |
| 19 | 542D0241 | P CUL CL D 1 36 | 34 | FOOT | $59.00 | $53.46 | $150.00 | |
| 20 | 54248510 | CONCRETE COLLAR | 4.2 | CU YD | $1,500.00 | $1,350.81 | $4,500.00 | |
| 21 | 63000001 | SPBGR TY A 6FT POSTS | 1,875 | FOOT | $25.00 | $23.12 | $27.00 | |
| 22 | 63000003 | SPBGR TY A 9FT POSTS | 9,262.5 | FOOT | $30.00 | $32.70 | $33.00 | |
| 23 | 63000009 | SPBGR TY B 9FT POSTS | 425 | FOOT | $51.00 | $52.22 | $45.00 | |
| 24 | 63000350 | LSG OV CUL 12'6" SPAN | 75 | FOOT | $40.00 | $134.27 | $27.00 | |
| 25 | 63100045 | TRAF BAR TERM T2 | 8 | EACH | $1,250.00 | $1,191.66 | $1,250.00 | |
| 26 | 63100075 | TRAF BAR TERM T5A | 9 | EACH | $1,000.00 | $1,413.57 | $1,050.00 | |
| 27 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $3,600.00 | $3,623.52 | $3,100.00 | |
| 28 | 63100167 | TR BAR TRM T1 SPL TAN | 215 | EACH | $3,000.00 | $3,524.48 | $3,000.00 | |
| 29 | 63100169 | TR BAR TRM T1 SPL FLR | 5 | EACH | $2,700.00 | $2,907.29 | $3,000.00 | |
| 30 | 63200310 | GUARDRAIL REMOV | 16,958 | FOOT | $7.00 | $4.99 | $6.50 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $75,000.00 | $83,056.39 | $145,000.00 | |
| 32 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $255,000.00 | $284,354.27 | $35,000.00 | |
| 33 | 72501000 | TERMINAL MARKER - DA | 220 | EACH | $30.00 | $24.70 | $35.00 | |
| 34 | 78200005 | GRDRAIL REF TYPE A | 364 | EACH | $10.00 | $3.09 | $8.00 |