18-00166-00-BR
- Let date
- Friday, June 16, 2023
- Contract
- 89779 · job page
- District
- District 4
- County
- Woodford
- Highway
- Limits
- Removal and replacement of a three-span and four-span PPC deck beam superstructure with concrete bent substructures, HMA approaches, on CH 7 over Panther Creek, 2.5 miles south of US 24.
- Classification
- ·
- Project number
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Otto Baum Company, Inc. Low bidder | $1,998,400 | ||
| 2 | Stark Excavating, Inc. | $2,086,174 | +4.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Otto Baum Compa… | #2 Stark Excavatin… |
|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.6 | ACRE | $8,133.27 | $6,800.00 | |
| 2 | X4401198 | HMA SURF REM VAR DP | 350 | SQ YD | $27.62 | $26.00 | |
| 3 | X5150110 | NAME PLATES SPL | 2 | EACH | $836.89 | $800.00 | |
| 4 | Z0001900 | ASB BEARING PAD REMOV | 154 | EACH | $26.69 | $12.00 | |
| 5 | Z0012754 | STR REP CON DP = < 5 | 125 | SQ FT | $291.88 | $275.00 | |
| 6 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $13,732.53 | $7,500.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 455 | CU YD | $63.49 | $51.00 | |
| 8 | 20300100 | CHANNEL EXCAVATION | 100 | CU YD | $90.55 | $16.00 | |
| 9 | 20400800 | FURNISHED EXCAVATION | 660 | CU YD | $83.89 | $69.00 | |
| 10 | 28100209 | STONE RIPRAP CL A5 | 685 | TON | $88.21 | $115.00 | |
| 11 | 28200200 | FILTER FABRIC | 575 | SQ YD | $4.91 | $6.00 | |
| 12 | 28300400 | AGGREGATE DITCH | 100 | TON | $111.45 | $100.00 | |
| 13 | 35650600 | BASE CSE WID VAR DP | 138 | SQ YD | $265.62 | $240.00 | |
| 14 | 40200800 | AGG SURF CSE B | 154 | TON | $45.85 | $82.00 | |
| 15 | 40600290 | BIT MATLS TACK CT | 705 | POUND | $2.12 | $2.00 | |
| 16 | 40604050 | HMA SC IL-9.5 C N50 | 437 | TON | $185.00 | $185.00 | |
| 17 | 40800050 | INCIDENTAL HMA SURF | 6 | TON | $318.74 | $305.00 | |
| 18 | 44004000 | PAVED DITCH REMOVAL | 90 | FOOT | $36.45 | $11.00 | |
| 19 | 48101200 | AGGREGATE SHLDS B | 288 | TON | $47.29 | $60.00 | |
| 20 | 50101500 | REM EXIST SUP-STR | 2 | EACH | $60,000.00 | $67,750.00 | |
| 21 | 50102400 | CONC REM | 9.1 | CU YD | $6,134.91 | $4,800.00 | |
| 22 | 50105220 | PIPE CULVERT REMOV | 96 | FOOT | $36.25 | $15.00 | |
| 23 | 50300225 | CONC STRUCT | 23.9 | CU YD | $3,000.00 | $4,280.00 | |
| 24 | 50400305 | P P CONC DK BM 17 DP | 4,760 | SQ FT | $106.00 | $116.75 | |
| 25 | 50400405 | P P CONC DK BM 21 DP | 4,305 | SQ FT | $111.00 | $120.00 | |
| 26 | 50800205 | REINF BARS, EPOXY CTD | 2,720 | POUND | $5.12 | $12.00 | |
| 27 | 50900205 | STEEL RAILING TY S1 | 618 | FOOT | $141.58 | $136.00 | |
| 28 | 542D0220 | P CUL CL D 1 15 | 40 | FOOT | $81.02 | $61.00 | |
| 29 | 542D0223 | P CUL CL D 1 18 | 80 | FOOT | $82.74 | $37.00 | |
| 30 | 58100200 | WATERPRF MEMBRANE SYS | 1,019 | SQ YD | $45.00 | $62.00 | |
| 31 | 58300100 | PC MORTAR FAIRING CSE | 685 | FOOT | $80.00 | $3.40 | |
| 32 | 59300100 | CONTR LOW-STRENG MATL | 44 | CU YD | $126.13 | $200.00 | |
| 33 | 63000001 | SPBGR TY A 6FT POSTS | 25 | FOOT | $36.66 | $35.00 | |
| 34 | 63100075 | TRAF BAR TERM T5A | 8 | EACH | $1,593.72 | $1,550.00 | |
| 35 | 63100167 | TR BAR TRM T1 SPL TAN | 8 | EACH | $2,921.82 | $2,800.00 | |
| 36 | 63200310 | GUARDRAIL REMOV | 416 | FOOT | $14.96 | $4.50 | |
| 37 | 67100100 | MOBILIZATION | 1 | L SUM | $111,505.88 | $123,660.00 | |
| 38 | 70300150 | SHRT TRM PAVT MK REM | 104 | SQ FT | $1.06 | $0.0100 | |
| 39 | 70306120 | TEMP PVT MK L4 T3 TAPE | 3,700 | FOOT | $1.49 | $0.0100 | |
| 40 | 72501000 | TERMINAL MARKER - DA | 8 | EACH | $53.12 | $52.00 | |
| 41 | 78001110 | PAINT PVT MK LINE 4 | 3,700 | FOOT | $0.9600 | $1.00 |