19-00906-99-DR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Phoenix Corporation of the Quad Cities Low bidder | $125,253 | ||
| 2 | Miller and Son Construction Co. | $196,300 | +56.7% | |
| 3 | Lee Hood d/b/a Hood Demolition & Excavation | $245,067 | +95.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Phoenix Corpora… | #2 Miller and Son … | #3 Lee Hood d/b/a … |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326837 | GRID REINFORC SLOPE | 374 | SQ YD | $13.00 | $64.00 | $286.00 | |
| 2 | X7011801 | TRAF CONT-PROT BLR 22 | 1 | L SUM | $8,200.00 | $8,500.00 | $3,500.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,700.00 | $8,000.00 | $5,845.00 | |
| 4 | Z0054500 | ROCK FILL | 110 | TON | $53.00 | $40.00 | $42.50 | |
| 5 | 20100500 | TREE REMOV ACRES | 0.25 | ACRE | $18,200.00 | $40,000.00 | $48,000.00 | |
| 6 | 20200100 | EARTH EXCAVATION | 340 | CU YD | $26.00 | $10.00 | $22.00 | |
| 7 | 20201200 | REM & DISP UNS MATL | 54 | CU YD | $45.00 | $50.00 | $60.00 | |
| 8 | 25000300 | SEEDING CL 3 | 0.25 | ACRE | $3,400.00 | $5,600.00 | $14,000.00 | |
| 9 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $4.00 | $6.00 | $7.00 | |
| 10 | 25000500 | PHOSPHORUS FERT NUTR | 23 | POUND | $4.00 | $6.00 | $7.00 | |
| 11 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $4.00 | $6.00 | $7.00 | |
| 12 | 25100127 | MULCH METHOD 3A | 0.25 | ACRE | $4,500.00 | $12,350.00 | $14,000.00 | |
| 13 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $3.50 | $4.00 | $3.00 | |
| 14 | 28000305 | TEMP DITCH CHECKS | 450 | FOOT | $8.00 | $11.00 | $8.89 | |
| 15 | 28000400 | PERIMETER EROS BAR | 62 | FOOT | $5.00 | $10.00 | $3.23 | |
| 16 | 28000500 | INLET & PIPE PROTECT | 1 | EACH | $150.00 | $500.00 | $400.00 | |
| 17 | 28100107 | STONE RIPRAP CL A4 | 8 | SQ YD | $160.00 | $300.00 | $100.00 | |
| 18 | 28200200 | FILTER FABRIC | 178 | SQ YD | $1.50 | $10.00 | $4.49 | |
| 19 | 28300400 | AGGREGATE DITCH | 100 | TON | $60.00 | $80.00 | $50.00 | |
| 20 | 35101400 | AGG BASE CSE B | 192 | TON | $32.00 | $70.00 | $35.00 | |
| 21 | 44004000 | PAVED DITCH REMOVAL | 112 | FOOT | $13.00 | $40.00 | $20.00 | |
| 22 | 48101500 | AGGREGATE SHLDS B 6 | 140 | SQ YD | $22.00 | $70.00 | $32.00 | |
| 23 | 50105220 | PIPE CULVERT REMOV | 156 | FOOT | $15.00 | $158.00 | $10.00 | |
| 24 | 542C3391 | P CUL CL C 5 36 | 120 | FOOT | $230.00 | $292.00 | $367.67 | |
| 25 | 63000003 | SPBGR TY A 9FT POSTS | 113 | FOOT | $55.00 | $52.25 | $60.00 | |
| 26 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $5,500.00 | $4,980.00 | $4,200.00 | |
| 27 | 63200310 | GUARDRAIL REMOV | 43 | FOOT | $11.00 | $40.00 | $10.00 | |
| 28 | 67100100 | MOBILIZATION | 1 | L SUM | $20,000.00 | $12,000.00 | $12,000.00 |