19-00382-00-SM
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $567,219 | ||
| 2 | D. Construction, Inc. | $612,554 | +8.0% | |
| 3 | Curran Contracting Company | $614,754 | +8.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… | #2 D. Construction… | #3 Curran Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $6,000.00 | $52,000.00 | $4,550.00 | |
| 2 | Z0055400 | RUMBLE STRIP | 28,620 | FOOT | $0.2200 | $0.3200 | $0.5000 | |
| 3 | 21101610 | TOPSOIL F & P 3 | 118 | SQ YD | $6.35 | $27.50 | $25.00 | |
| 4 | 40600275 | BIT MATLS PR CT | 120 | POUND | $4.50 | $0.0100 | $0.0100 | |
| 5 | 40600290 | BIT MATLS TACK CT | 23,992 | POUND | $0.6500 | $0.0100 | $0.0100 | |
| 6 | 40600370 | LONG JOINT SEALANT | 15,457 | FOOT | $2.65 | $2.62 | $2.45 | |
| 7 | 40600982 | HMA SURF REM BUTT JT | 837 | SQ YD | $17.25 | $0.0100 | $11.50 | |
| 8 | 40602965 | HMA BC IL-9.5FG N50 | 2,501 | TON | $78.00 | $80.00 | $72.50 | |
| 9 | 40604000 | HMA SC IL-9.5FG C N50 | 2,582 | TON | $83.00 | $80.00 | $92.50 | |
| 10 | 44000154 | HMA SURF REM 1 1/4 | 191 | SQ YD | $9.00 | $25.00 | $11.50 | |
| 11 | 44000159 | HMA SURF REM 2 1/2 | 175 | SQ YD | $15.00 | $25.00 | $11.50 | |
| 12 | 48102100 | AGG WEDGE SHLD TYPE B | 1,122 | TON | $26.00 | $32.00 | $39.75 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $20,000.00 | $34,670.00 | $59,500.00 | |
| 14 | 70300100 | SHORT TERM PAVT MKING | 15,440 | FOOT | $0.7000 | $0.5000 | $0.3000 | |
| 15 | 78001110 | PAINT PVT MK LINE 4 | 15,335 | FOOT | $0.1500 | $0.2200 | $0.2000 | |
| 16 | 78001130 | PAINT PVT MK LINE 6 | 30,141 | FOOT | $0.2200 | $0.3300 | $0.3000 |