18-00140-00-RS
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $397,927 | ||
| 2 | H. J. Eppel & Co. | $460,673 | +15.8% | |
| 3 | Cross Construction, Inc. | $485,083 | +21.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 H. J. Eppel & C… | #3 Cross Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | 40600290 | BIT MATLS TACK CT | 9,855 | POUND | $0.0100 | $1.00 | $0.8000 | |
| 2 | 40600990 | TEMPORARY RAMP | 40 | SQ YD | $0.0100 | $29.00 | $150.00 | |
| 3 | 40604050 | HMA SC IL-9.5 C N50 | 2,740 | TON | $93.00 | $117.00 | $113.00 | |
| 4 | 40800050 | INCIDENTAL HMA SURF | 20 | TON | $375.00 | $370.00 | $300.00 | |
| 5 | 44000159 | HMA SURF REM 2 1/2 | 22,060 | SQ YD | $3.50 | $3.15 | $4.00 | |
| 6 | 48101200 | AGGREGATE SHLDS B | 550 | TON | $41.50 | $39.00 | $41.00 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $23,000.00 | $9,600.00 | $13,000.00 | |
| 8 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $8,000.00 | $13,250.00 | $18,000.00 | |
| 9 | 70300100 | SHORT TERM PAVT MKING | 2,665 | FOOT | $0.0100 | $0.7500 | $1.40 | |
| 10 | 70300150 | SHRT TRM PAVT MK REM | 295 | SQ FT | $0.0100 | $3.90 | $12.00 | |
| 11 | 78001110 | PAINT PVT MK LINE 4 | 5,925 | FOOT | $0.7500 | $0.8000 | $1.10 |