15-00760-00-BR
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | D. Construction, Inc. Low bidder | $4,537,912 | ||
| 2 | ICC Group Inc. | $6,160,200 | +35.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 D. Construction… | #2 ICC Group Inc. |
|---|---|---|---|---|---|---|---|
| 1 | X0320051 | CROS SONIC LOG A DUCT | 1,838 | FOOT | $16.00 | $24.00 | |
| 2 | X0320052 | CROS SONIC LOG TEST | 8 | EACH | $1,550.00 | $2,000.00 | |
| 3 | X0326649 | LINEAR DELIN PANELS 6 | 10 | EACH | $82.50 | $75.00 | |
| 4 | X0327638 | STREAM GAUGE | 1 | EACH | $15,000.00 | $11,195.00 | |
| 5 | X2020410 | EARTH EXCAVATION SPL | 750 | CU YD | $35.00 | $36.00 | |
| 6 | X2501000 | SEEDING CL 2 SPL | 1.31 | ACRE | $2,233.00 | $2,500.00 | |
| 7 | X2600022 | REM ST RE SNPLASSY SP | 4 | EACH | $495.00 | $450.00 | |
| 8 | X2810210 | STONE RIPRAP CL A5 SP | 557 | TON | $57.50 | $118.00 | |
| 9 | X2810212 | STONE RIPRAP CL A6 SP | 2,816 | TON | $70.00 | $122.00 | |
| 10 | X4023000 | TEMP ACCESS- ROAD | 1 | EACH | $35,000.00 | $24,985.00 | |
| 11 | X5211435 | HLMRB DISC FIXED 700K | 5 | EACH | $6,500.00 | $8,870.00 | |
| 12 | X5211635 | HLMRB DISC G EXP 700K | 5 | EACH | $7,000.00 | $10,265.00 | |
| 13 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $15,000.00 | $10,500.00 | |
| 14 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $28,660.00 | $41,750.00 | |
| 15 | Z0076600 | TRAINEES | 1,000 | HOUR | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | |
| 17 | 20100500 | TREE REMOV ACRES | 0.85 | ACRE | $12,100.00 | $35,000.00 | |
| 18 | 20201200 | REM & DISP UNS MATL | 110 | CU YD | $30.00 | $50.00 | |
| 19 | 20300100 | CHANNEL EXCAVATION | 3,962 | CU YD | $25.00 | $50.00 | |
| 20 | 21101615 | TOPSOIL F & P 4 | 4,347 | SQ YD | $6.60 | $6.45 | |
| 21 | 25100630 | EROSION CONTR BLANKET | 6,234 | SQ YD | $1.10 | $1.30 | |
| 22 | 28000250 | TEMP EROS CONTR SEED | 131 | POUND | $5.50 | $15.80 | |
| 23 | 28000400 | PERIMETER EROS BAR | 1,030 | FOOT | $2.20 | $4.00 | |
| 24 | 28100207 | STONE RIPRAP CL A4 | 240 | TON | $60.00 | $80.00 | |
| 25 | 28200200 | FILTER FABRIC | 139 | SQ YD | $3.00 | $4.00 | |
| 26 | 28300400 | AGGREGATE DITCH | 119 | TON | $30.00 | $47.00 | |
| 27 | 30300011 | AGG SUBGRADE IMPROVE | 891 | TON | $25.00 | $40.00 | |
| 28 | 40200800 | AGG SURF CSE B | 56 | TON | $25.00 | $38.00 | |
| 29 | 40600275 | BIT MATLS PR CT | 3,325 | POUND | $0.0100 | $1.50 | |
| 30 | 40600290 | BIT MATLS TACK CT | 335 | POUND | $0.0100 | $4.00 | |
| 31 | 40603080 | HMA BC IL-19.0 N50 | 249 | TON | $90.00 | $150.00 | |
| 32 | 40604050 | HMA SC IL-9.5 C N50 | 93 | TON | $100.00 | $280.00 | |
| 33 | 42000070 | PVT CON HMA BR APP SL | 68 | SQ YD | $85.00 | $155.00 | |
| 34 | 44000100 | PAVEMENT REM | 1,478 | SQ YD | $10.00 | $10.50 | |
| 35 | 48101200 | AGGREGATE SHLDS B | 195 | TON | $30.00 | $48.00 | |
| 36 | 48203019 | HMA SHOULDERS 5 1/2 | 356 | SQ YD | $30.00 | $55.00 | |
| 37 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $150,000.00 | $500,000.00 | |
| 38 | 50100400 | REM EXIST STRUCT N2 | 1 | EACH | $15,000.00 | $13,500.00 | |
| 39 | 50200100 | STRUCTURE EXCAVATION | 475 | CU YD | $30.00 | $50.00 | |
| 40 | 50300100 | FLOOR DRAINS | 34 | EACH | $550.00 | $945.00 | |
| 41 | 50300225 | CONC STRUCT | 381.4 | CU YD | $800.00 | $1,175.00 | |
| 42 | 50300255 | CONC SUP-STR | 406.4 | CU YD | $950.00 | $1,425.00 | |
| 43 | 50300260 | BR DECK GROOVING | 1,156 | SQ YD | $7.00 | $6.23 | |
| 44 | 50300300 | PROTECTIVE COAT | 1,578 | SQ YD | $1.00 | $2.75 | |
| 45 | 50301350 | CONC SUPSTR APP SLAB | 88.9 | CU YD | $460.00 | $545.00 | |
| 46 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $1,300,379.00 | $1,485,780.98 | |
| 47 | 50500505 | STUD SHEAR CONNECTORS | 8,980 | EACH | $5.00 | $4.50 | |
| 48 | 50800205 | REINF BARS, EPOXY CTD | 253,070 | POUND | $2.25 | $2.00 | |
| 49 | 50800515 | BAR SPLICERS | 492 | EACH | $47.85 | $60.00 | |
| 50 | 50900105 | ALUM RAILING TY L | 623 | FOOT | $186.82 | $175.00 | |
| 51 | 51200958 | FUR M S PILE 14X0.250 | 880 | FOOT | $82.00 | $95.00 | |
| 52 | 51202305 | DRIVING PILES | 848 | FOOT | $0.0100 | $0.1000 | |
| 53 | 51203200 | TEST PILE MET SHELLS | 2 | EACH | $5,000.00 | $9,850.00 | |
| 54 | 51500100 | NAME PLATES | 1 | EACH | $700.00 | $800.00 | |
| 55 | 51602000 | PERMANENT CASING | 372 | FOOT | $340.00 | $380.00 | |
| 56 | 51603000 | DRILLED SHAFT IN SOIL | 326.8 | CU YD | $250.00 | $300.00 | |
| 57 | 51604000 | DRILLED SHAFT IN ROCK | 64 | CU YD | $2,150.00 | $5,607.00 | |
| 58 | 52100520 | ANCHOR BOLTS 1 | 20 | EACH | $140.00 | $215.00 | |
| 59 | 52100530 | ANCHOR BOLTS 1 1/4 | 40 | EACH | $180.00 | $225.00 | |
| 60 | 58600101 | GRANULAR BACKFILL STR | 172 | CU YD | $50.00 | $75.00 | |
| 61 | 59100100 | GEOCOMPOSITE WALL DR | 55 | SQ YD | $35.00 | $55.00 | |
| 62 | 60100060 | CONC HDWL FOR P DRAIN | 8 | EACH | $450.00 | $845.00 | |
| 63 | 60108100 | PIPE UNDERDRAIN 4 SP | 40 | FOOT | $35.00 | $53.00 | |
| 64 | 60108501 | PIPE UNDERDR T 3 | 904 | FOOT | $20.00 | $22.00 | |
| 65 | 60146304 | P UNDR FOR STRUCT 4 | 122 | FOOT | $20.00 | $40.00 | |
| 66 | 63000001 | SPBGR TY A 6FT POSTS | 412.5 | FOOT | $36.59 | $33.26 | |
| 67 | 63100085 | TRAF BAR TERM T6 | 4 | EACH | $4,508.90 | $4,099.00 | |
| 68 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,939.10 | $3,581.00 | |
| 69 | 63100169 | TR BAR TRM T1 SPL FLR | 2 | EACH | $3,718.00 | $3,380.00 | |
| 70 | 63200310 | GUARDRAIL REMOV | 773 | FOOT | $6.36 | $5.78 | |
| 71 | 67100100 | MOBILIZATION | 1 | L SUM | $270,000.00 | $350,000.00 | |
| 72 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $38.50 | $35.00 | |
| 73 | 78001110 | PAINT PVT MK LINE 4 | 3,300 | FOOT | $0.9900 | $0.9000 | |
| 74 | 78200006 | GRDRAIL REF TYPE B | 13 | EACH | $11.00 | $10.00 |