23-00117-00-RS
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Rock Road Companies, Inc. Low bidder | $636,212 | ||
| 2 | Curran Contracting Company | $653,052 | +2.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Rock Road Compa… | #2 Curran Contract… |
|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,527.55 | $5,500.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,572.82 | $8,900.00 | |
| 3 | 20200600 | EXC & GR EX SHOULDER | 81 | UNIT | $283.48 | $515.00 | |
| 4 | 21101600 | TOPSOIL F & P VAR DP | 8,450 | SQ YD | $4.27 | $4.25 | |
| 5 | 25000110 | SEEDING CL 1A | 1.8 | ACRE | $2,010.02 | $2,000.00 | |
| 6 | 25000400 | NITROGEN FERT NUTR | 162 | POUND | $4.02 | $4.00 | |
| 7 | 25000500 | PHOSPHORUS FERT NUTR | 162 | POUND | $4.02 | $4.00 | |
| 8 | 25000600 | POTASSIUM FERT NUTR | 162 | POUND | $4.02 | $4.00 | |
| 9 | 25100115 | MULCH METHOD 2 | 1.8 | ACRE | $2,010.02 | $2,000.00 | |
| 10 | 28000250 | TEMP EROS CONTR SEED | 180 | POUND | $5.03 | $5.00 | |
| 11 | 28000400 | PERIMETER EROS BAR | 13,314 | FOOT | $2.51 | $2.50 | |
| 12 | 40600290 | BIT MATLS TACK CT | 30,200 | POUND | $0.3800 | $0.0100 | |
| 13 | 40600370 | LONG JOINT SEALANT | 16,492 | FOOT | $2.60 | $2.65 | |
| 14 | 40600982 | HMA SURF REM BUTT JT | 1,073 | SQ YD | $7.54 | $17.50 | |
| 15 | 40600990 | TEMPORARY RAMP | 33 | SQ YD | $24.48 | $15.00 | |
| 16 | 40602970 | HMA BC IL-9.5FG N70 | 1,503 | TON | $83.43 | $69.40 | |
| 17 | 40604062 | HMA SC IL-9.5 D N70 | 1,796 | TON | $82.41 | $69.40 | |
| 18 | 40800050 | INCIDENTAL HMA SURF | 132 | TON | $126.28 | $160.00 | |
| 19 | 44000155 | HMA SURF REM 1 1/2 | 11,932 | SQ YD | $2.83 | $2.25 | |
| 20 | 44000200 | DRIVE PAVEMENT REM | 29 | SQ YD | $30.25 | $20.00 | |
| 21 | 48101200 | AGGREGATE SHLDS B | 2,645 | TON | $0.0100 | $13.00 | |
| 22 | 48203013 | HMA SHOULDERS 4 | 2,006 | SQ YD | $21.67 | $23.25 | |
| 23 | 64200108 | SHOULDER RUM STRIP 8 | 13,314 | FOOT | $1.08 | $0.6000 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $53,328.00 | $65,000.00 | |
| 25 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $402.00 | $400.00 | |
| 26 | 70300100 | SHORT TERM PAVT MKING | 5,460 | FOOT | $0.9200 | $0.3000 | |
| 27 | 78000200 | THPL PVT MK LINE 4 | 14,410 | FOOT | $0.7000 | $0.7000 | |
| 28 | 78000400 | THPL PVT MK LINE 6 | 6,840 | FOOT | $1.06 | $1.05 |