18-00376-00-GR
- Let date
- Friday, September 18, 2020
- Contract
- 85696 · job page
- District
- District 2
- County
- Rock Island
- Highway
- Limits
- Remove and replace guardrail and terminals at various locations in Rock Island County.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lovewell Fencing, Inc. Low bidder | $1,125,972 | ||
| 2 | COLLINS & HERMANN, INC. | $1,200,314 | +6.6% | |
| 3 | Northern Contracting, Inc. | $1,255,283 | +11.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lovewell Fencin… | #2 COLLINS & HERMA… | #3 Northern Contra… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 3.15 | ACRE | $3,100.00 | $5,000.00 | $5,000.00 | |
| 2 | X6330725 | SPBGR (SHORT RADIUS) | 583 | FOOT | $100.00 | $60.04 | $27.83 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $18,500.00 | $121,745.71 | $195,400.00 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $7,000.00 | $6,351.41 | $15,000.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 87 | CU YD | $46.00 | $28.00 | $28.00 | |
| 6 | 20400800 | FURNISHED EXCAVATION | 1,168 | CU YD | $60.00 | $75.00 | $75.00 | |
| 7 | 35101400 | AGG BASE CSE B | 73 | TON | $100.00 | $100.00 | $100.00 | |
| 8 | 44000161 | HMA SURF REM 3 | 6,226 | SQ YD | $8.75 | $15.50 | $15.50 | |
| 9 | 48101200 | AGGREGATE SHLDS B | 894 | TON | $44.00 | $65.25 | $65.25 | |
| 10 | 48203100 | HMA SHOULDERS | 1,074 | TON | $202.88 | $144.50 | $144.50 | |
| 11 | 63000003 | SPBGR TY A 9FT POSTS | 8,921 | FOOT | $28.00 | $25.68 | $28.45 | |
| 12 | 63000350 | LSG OV CUL 12'6" SPAN | 450 | FOOT | $25.00 | $23.23 | $27.33 | |
| 13 | 63100045 | TRAF BAR TERM T2 | 20 | EACH | $1,400.00 | $1,135.91 | $1,280.00 | |
| 14 | 63100075 | TRAF BAR TERM T5A | 3 | EACH | $1,000.00 | $1,206.02 | $900.00 | |
| 15 | 63100167 | TR BAR TRM T1 SPL TAN | 46 | EACH | $3,200.00 | $3,291.17 | $3,115.00 | |
| 16 | 63200310 | GUARDRAIL REMOV | 9,347 | FOOT | $6.00 | $7.47 | $7.90 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $141,218.00 | $125,438.39 | $91,000.00 | |
| 18 | 72501000 | TERMINAL MARKER - DA | 46 | EACH | $30.00 | $24.60 | $35.00 | |
| 19 | 78200005 | GRDRAIL REF TYPE A | 140 | EACH | $10.00 | $3.08 | $10.00 |